PIC负责人SevrtechAreaConstructionManager区域施工经理Siteconstructionmanager现场施工经理RAWeight≥25T,butloading<75%oftheratedcranecapacity重量≥25T,但负载<吊车额定负载的75%RAloading≥75%oftheratedcranecapacity负载≥吊车额定负载的75%RATwoormorecranesareusedforthesamelift两台或多台吊车用于同一起吊RAWheneverpersonnelarebeinghoisted载人时RAWhenusingadjustabledevice(examples:chainhoists,comealongs,turnbuckles)forunusualshapeobjectslifting使用可调节设备(如手拉葫芦、伸线器、紧镙器)起吊形状不规则物体时RABlindlifting盲吊RALiftingoveroraround(<10m)livepowerlines在(<10m)带电电线上空或周围吊装时RATitle名称Normalliftingplan正常吊装计划(Weight<25Tandloading<75%oftheratedcranecapacity)(重量<25T,负载<吊车额定负载的75%)LiftingPlanReviewandApprovalResponsibilityMatrix吊装计划审核批准责任表CriticalLiftingPlan临界吊装计划R=Review审核A=Approval批准