作业指导书工程名称:内蒙古大唐国际托克托电厂五期扩建工程编号:X-005作业项目名称:#10机组除氧器吊装作业编制单位:中能建江苏省电力建设第一工程有限公司大唐托电项目部编写:日期:审核:日期:审定:日期:日期:批准:日期:出版日期:版次:第一版#10机组除氧器吊装(X-005)1/17目录1适用范围·······························································22编制依据·······························································23主要工程量·····························································24组织机构和作业人员的资格要求···········································25主要机械及工器具·······················································46施工进度·······························································47施工准备·······························································48作业程序·······························································59作业方法、工艺要求及质量标准···········································510相关计算··························································711工序交接及成品保护····················································912安全和文明施工措施····················································913强制性条文····························································1014应急处置方案··························································11附表:重大危险源/重要环境因素控制计划表···································14#10机组除氧器吊装(X-005)2/171适用范围本作业指导书适用于指导和实施我公司承建的内蒙古大唐国际托克托电厂五期扩建工程10#机组除氧器吊装作业。2编制依据《除氧器安装图》图号:F211102S-J0302-11《CC2500(450t)履带吊使用说明书》《FZQ1380(63t)塔式起重机使用说明书》《起重机械安全规程》GB6067.1—2010《电力建设安全工作规程》火力发电厂部分DL5009.1-2014《特种设备安全法》2014年1月1日起施行《起重机械安全规程》GB6067.1—2010《特种设备作业人员监督管理办法》国家质量监督检验检疫总局令第140号《起重机械监督检验规程》国家质量监督检验检疫总局《大唐托克托电厂五期扩建工程第二标段施工组织设计》江苏电建一公司《大唐托克托电厂五期扩建工程施工总平面图》引用标准GB/T706-2008、GB/T8919-2006、GB/T20067-2006等3主要工程量内蒙古大唐国际托克托电厂五期扩建工程10#机组除氧器采用滑压运行,正常运行由汽轮机四段抽汽供汽,启动或低负荷时由辅助蒸汽系统供汽。本期机组汽机房不设除氧间,除氧器布置在锅炉房K0-K1钢架上。除氧器外形尺寸为26100mm×4360mm×4500mm,净重约为95t。就位轴向中心线标高44851mm,基础支座平面标高为41300mm,距离K1钢柱中心4238mm。钢架立柱G3-G5排柱中心距离28000mm,实际净吊装距离为27300mm,根据设备到货和锅炉安装情况,决定由450t履带吊单机吊装除氧器直接落在元宝座上就位。除氧器采用450t履带吊卸车。4组织机构和作业人员的资格要求4.1组织机构以江苏电建一公司大唐托克托项目部为依托,按照以下表格内要求抽调专业骨干实施作业。为保证吊装安全,特成立“大唐托克托项目部#10除氧器吊装”专项组织机构,见下表:#10机组除氧器吊装(X-005)3/17序号姓名分工职务/职称1吕从军吊装总负责人副经理/高工2翁庆松现场安全管理安全科长3李安保吊装区域安全监督安全员4丁兴宏吊装机械安全监督机修工地安全员5毕正斌安装负责人机炉工地主任6孙逸诚施工协调工程科科长7邓海雄吊装负责人机修工地主任8陆茂生起重总指挥机炉工地起重班长9林大亮方案编制、技术指导机修工地专工10丁庆涛现场应急预案准备办公室主任总负责:孙卫东总工安保负责:翁庆松机械负责:邓海雄作业负责:毕正斌后勤负责:丁庆涛协调负责:孙逸诚监护实施:郭一飞操作作业组:汪国强起重作业组:陆茂生安装作业组:黄树才4.2劳动力计划和作业人员的资格要求序号工种技术等级数量特殊工种上岗证备注1电工中级工1电工证监护现场供电2钳工中级工2监护履带吊3起重指挥中级工2起重指挥证除氧器吊装指挥4起重司索初级工4起重司索证除氧器吊装司索5操作工中级工6起重机械操作操作起重机械6安装工初、中级工4安装除氧器7架子工初、中级工4架子工证7安全员2安全员证安全监护8电风焊工中级工2焊工证加固焊接9总指挥高级工1协调吊装作业#10机组除氧器吊装(X-005)4/1710技术员中级1措施、技术交底5主要机械及工器具序号名称规格型号数量备注1履带式起重机450t一台吊装2塔式起重机1380/63tT一台辅助3卸扣35t4只4千斤绳6×37-170-φ65mm2对30m5钢丝绳6×37-170-17.5mm400m6钢丝绳φ20mm20m/对2对7溜绳60m2根8风焊工具2套9链条葫芦5t、2t若干10千斤顶100t4只11捆绑绳若干12卷尺5m若干6施工进度本项目预计12月底开始准备,1月初完成吊装。7施工准备7.1履带吊工作场地准备:锅炉钢架验收合格,扩建端场地平整、压实后铺好路基板,满足履带吊作业。7.2吊车准备CC2500(450t)履带吊SWSL工况,接54m主臂、30m副臂、配重120t、超级配重140t,超起半径15m、超起副臂30m。履带吊幅度工况性能如下表。幅度m28m30m32m34m起重量t12611610899CC2500(450t)履带吊SSL工况,接54m主臂、中心配重30t,配重140t,超起半径15m、超起臂30m。履带吊幅度工况性能如下表。幅度m10m12m14m16m起重量t242179140114FZQ1380塔吊,回转半径25米,最大起重量52.8t。#10机组除氧器吊装(X-005)5/177.3除氧器及吊车停放在除氧间外侧托运轴线方向,按图一布置要求停放:图一:450t履带吊起吊除氧器卸车7.4现场条件准备7.4.1环境准备i灭火器等器材已定址放置。ii施工电源布置完成。iii通道畅通,光线充足,安全设施工作状态良好,氧乙炔供应充足。iv安装区域平台完善,格栅板铺设完毕,预留孔洞装设盖板,无妨碍施工的任何物品。7.4.2安全条件i设立临时警戒区域,派专人监护,无关人员不得入内。ii吊装、托运用具、支座滚柱必须检查应满足安全使用要求。iii安全防护设施及安全用具(安全带等)必须符合安全使用要求。iv所有参加作业人员必须经过三级安全教育,高空作业人员必须经过体检合格后方可参加作业。作业前必须对所有参加人员进行安全、技术和质量交底。8作业程序#10机组除氧器吊装(X-005)6/17锅炉钢架设施验收合格450t履带吊就位除氧器卸车450t履带吊就位除氧器吊装找正安装就位9作业方法、工艺要求及质量标准9.1除氧器由450t履带吊卸车时,接54m主臂、配重140t,超起半径15m、超起副臂30m,回转半径13m,最大起重量140t,单机起吊,钢丝绳钩头重约8t,吊装总重约为103t,负荷率约73.6%,满足要求。9.2除氧器吊装时,用一台450t履带吊(接54m主臂、30m副臂、配重120t、超级配重100t,超起半径15m、超起副臂30m),回转半径22m,最大起重量140t,单机起吊,钢丝绳钩头重约8t,吊装总重约为103t,负荷率约73.6%,满足要求。起吊前应检查起重机械及其安全装置;除氧器吊离地面约10cm时应暂停起吊并进行全面检查和试验刹车,确认正常后方可正式起吊。第一步:450t履带吊带100t超级配重,除氧器缓慢起吊,待超过除氧器就位层41.3m约10cm后停止起吊。第二步:450t履带吊幅度不变,沿走道板方向缓慢向前移动21.1m,待除氧器到达KO、K1轴线上方,停止移动。第三步:450t履带吊增加40t超级配重(由1380塔吊在25m幅度吊装4块10t超级配重,负荷率为18%),超级配重总重140t,然后缓慢变幅至32m,除氧器达到就位位置上方,找准就位中心,缓慢的将除氧器放在固定的元宝型支座上。450t履带吊,回转半径32m,额定起重量为108t,负荷率为95.3%,满足要求。见下图三:#10机组除氧器吊装(X-005)7/17图二:吊装立面图图三:起吊平面图#10机组除氧器吊装(X-005)8/17图四:就位平面图9.5施工过程要求。施工作业人员必须按图纸、有关规程规范和作业指导书要求进行施工。在施工过程中对有疑问不清楚之处及时反馈给施工总指挥,不得盲目施工。在施工过程中如发现问题需立即向技术人员及现场指挥人员汇报,不得擅自施工。10相关计算10.1钢丝绳校核在吊装过程中除氧器净重95t,履带吊选用6×37+FC-1870-φ65mm千斤绳破断拉力T=254t。千斤绳起吊夹角220(见下图七),则钢丝绳单根受力:N=95/(4·COS11º)=95/(4×0.98)=24.2t吊装钢丝绳的安全系数K,K=T/N=254/24.2=10.498满足要求。钢丝绳夹角图五:钢丝绳夹角示意图#10机组除氧器吊装(X-005)9/1710.4除氧器卸车要求高度:图六:卸车高度幅度校核除氧器卸车时,450t起吊后,吊装高度剩余30m,除氧器距离履带吊主臂7.5m,满足吊装要求。11工序交接及成品保护除氧器吊装过程中,钢丝绳生钩过程等不得对除氧器造成损伤,做好保护,对各施工阶段所需物品应提前准备;各施工阶段结束后应核查是否达到预计效果,判断能否进行下一工序施工。12安全和文明施工措施12.1技术人员应在起吊作业前进行安全、技术、质量交底,交底时分公司总工、安全科、工程科、机修工地、机炉工地及甲方、监理有关人员到场,起吊前应开好安全作业票。12.2划定工作区域,并派专人监护,无关人员不得入内,不得在危险区域内逗留或通过。现场吊装应由专人指挥,指挥信号应统一,分工明确,信号清楚。12.3除氧器吊装前,必须先将元宝座安装在锅炉钢架上,保证除氧器顺利就位。12.4因现场情况复杂,现场施工区域内应清理干净、清理与施工无关的杂物。12.5起吊用索具必须检查,确保索具合格后再进行作业。起吊前认真检查吊机,尤其是#10机组除氧器吊装(X-005)10/17力矩限制器及各限位等安全装置,以保证机械机况的完好。12.6起吊、行走回转及脱钩等过程一定要缓慢,特别注意工序步骤的衔接。12.7施工过程中要有专人监护吊机卷扬机。12.8高空作业施工人员必须系好安全带,并牢固地挂在施工作业区的上方牢固处。高处作业的平台、走道、斜道等应装设由上下两道栏杆和栏杆组成的防护栏杆及档脚板,或设防护立网。12.9高处作业所用工具必须系安全绳,传递物件禁止抛掷,设备、材料及废料临时存放在要有可靠的防止移动和坠落的措施
本文标题:除氧器吊装(450T)1216
链接地址:https://www.777doc.com/doc-1955094 .html