您好,欢迎访问三七文档
当前位置:首页 > 建筑/环境 > 工程监理 > 京沪高铁线下工程沉降变形观测及评估实施方案
京沪高速铁路线下工程沉降变形观测及评估实施方案铁道部京沪高速铁路建设总指挥部京沪高速铁路股份有限公司二〇〇八年五月i目录第一章总则............................................................................................1一、适用范围......................................................................................1二、工作依据......................................................................................1第二章组织管理....................................................................................3一、职责分工......................................................................................3(一)建设单位.....................................3(二)施工单位.....................................3(三)监理单位.....................................4(四)设计单位.....................................5(五)咨询单位.....................................5(六)评估单位.....................................5二、工作程序......................................................................................6(一)施工单位.....................................6(二)监理单位.....................................6(三)设计单位.....................................7(四)咨询单位.....................................7(五)评估单位.....................................7(六)建设单位.....................................8第三章通用要求....................................................................................9一.沉降变形测量等级及精度要求..................................................9二.沉降变形监测网主要技术要求及建网方式..............................9三.沉降变形测量点的布置要求....................................................12四.沉降变形监测测量工作基本要求............................................12五.沉降变形监测观测具体要求....................................................13六.沉降变形监测平行检测工作....................................................15第四章专业要求..................................................................................16一、路基工程....................................................................................16(一)路基沉降变形观测............................16(二)路基工程沉降评估............................24(三)过渡段沉降变形观测..........................27(四)过渡段的沉降评估............................28二、桥涵工程....................................................................................28(一)一般规定....................................28(二)桥涵沉降变形控制标准........................29(三)沉降变形观测方案............................30(四)观测资料要求................................34(五)观测频次....................................35(六)沉降评估....................................37(七)其他........................................39三、隧道工程....................................................................................40(一)一般规定....................................40(二)沉降观测的内容..............................40(三)沉降观测点的布置............................40(四)观测精度....................................41(五)沉降观测频度................................41(六)沉降评估....................................42四、综合评估....................................................................................44五、区域沉降....................................................................................44附件一:线下工程沉降变形观测及评估流程图............................46附件二:资料传递程序....................................................................48附件三:各单位责任人名单............................................................50附件四:附表....................................................................................51附表1工程沉降变形观测准备工作检查记录表.........51附表2工程沉降变形观测结果评估验收记录表.........52附表3路基沉降水准测量记录表.....................53附表4路基沉降观测记录表(沉降观测桩)...........54附表5路基观测桩沉降量记录汇总表.................55附表6路基沉降观测记录表(沉降板)...............56附表7路基沉降板观测记录汇总表(沉降板).........57附表8路基沉降板观测记录表(剖面管).............58附表9路基分层沉降观测记录表.....................59附表10路基分层沉降观测记录汇总表................60附表11路基边桩位移观测记录表....................61附表12路基边桩位移观测记录汇总表................62附表13过渡段沉降量记录汇总表....................63附表14桥梁墩台沉降观测汇总表....................64附表15桥梁墩(台)沉降量记录表..................65附表16桥梁墩(台)沉降量记录汇总表..............66附表17涵洞沉降量记录表..........................67附表18涵洞沉降量记录汇总表......................68附表19隧道沉降量记录表..........................69附表20隧道沉降量记录汇总表......................70附表21横剖面沉降测试记录表......................711第一章总则为指导京沪高速铁路做好无砟轨道的铺设工作,通过对路基(含过渡段)、桥梁、涵洞、隧道等线下工程的沉降变形进行观测,并对观测资料进行分析,包括预测工后沉降,以便对无砟轨道的铺设条件进行评估,从而确定合理的无砟轨道铺设时机,确保无砟轨道结构的安全。无砟轨道铺设条件评估的重点应是线下工程的沉降变形,评估应综合考虑沿线路方向各种结构物间的沉降变形关系,以标段为单位实施。设计单位按照本指导方案,以标段为单位制定沉降观测设计方案。无砟轨道铺设条件的评估数据必须采用先进、成熟、科学的检测手段取得,且必须真实可靠,全面反映工程实际状况。沉降变形观测、评估过程是确定铺设无砟轨道的关键时间节点和关键工序的主要依据之一,必需加强“零观测”(即初始值)的过程控制。一、适用范围本方案适用于京沪高速铁路路基(含过渡段)、桥梁、涵洞、隧道工程施工过程中的沉降变形观测及评估。二、工作依据1.《客运专线铁路无砟轨道铺设条件评估技术指南》(铁建设[2006]158号);2.《客运专线铁路无砟轨道测量技术暂行规定》(铁建设[2006]189号);23.《国家一、二等水准测量规范》(GB12897—2006);4.《建筑沉降变形测量规程》(JGJ/T8-2007);5.《铁路客运专线竣工验收暂行办法》(铁建设[2007]183号);6.《客运专线无砟轨道铁路施工技术指南》(TZ216-2007);7.《工程测量规范》(GB0026-93);8.《全球定位系统(GPS)铁路测量规程》(TB10054-97);9.《客运专线无砟轨道铁路设计指南》(铁建设函[2005]754号);10.京沪高速铁路工程设计文件;11.铁道部有关规定。3第二章组织管理一、职责分工京沪高速铁路线下工程沉降变形观测及其评估工作,是一项系统工程,需要参建各方各负其责、密切配合,确保观测数据及评估结果的真实、可靠。(一)建设单位建设单位负责沉降变形观测及其评估工作的领导和协调,并对过程进行监督检查。1.总指挥部负责全线线下工程的沉降变形观测及其评估工作的领导和协调工作,对沉降变形观测及其评估过程进行监督检查。2.各指挥部负责各自管段内线下工程的沉降变形观测及其评估的组织工作,对沉降变形观测及其评估过程进行监督检查。3.必要时组织专家对评估报告进行评审。(二)施工单位施工单位是沉降变形观测的实施责任主体,必须严格按有关规范、设计文件及总指要求做好各项工程施工过程的沉降变形观测,对观测数据的真实性负责。1.负责
本文标题:京沪高铁线下工程沉降变形观测及评估实施方案
链接地址:https://www.777doc.com/doc-3259006 .html