中国电力工程有限公司(CNEEC)泰国TPIPP150MW电厂工程(TPIPP150MWPowerPlant)四大管道施工方案报审表FourpipelineconstructionplanReportform编号(NO.):[SPESC]-FABS-QJ-016日期(Date):2017YY年MM月DD日致:泰国TPIPP150MW电厂工程项目监理部To:TPIPP150MWPowerPlantSupervisionunit我方已完成四大管道施工方案的编制,并按规定完成相关审批手续,请予以审查。WehavecompletedFourpipelineconstructionplanofthetowercrane,andcompletetherelevantformalitiesofexaminationandapprovalinaccordancewiththeregulations,pleasereviewit.附(Attached):□施工组织设计(中英文)constructionorganizationdesign(Chinese-English)□专项施工方案(中英文)specialconstructionplan(Chinese-English)□施工方案(中英文)Theconstructionscheme(Chinese-English).□其他(中英文)Others(Chinese-English)分包单位(盖章)Subcontractingunit(Chapter)项目负责人(签字):Projectleader(Signature)YY年MM月DD日审查意见:Reviewcomments:专业监理工程师(签字):Professionalsupervisionengineer(Signature)YY年MM月DD日审核意见:Reviewcomments:项目监理部(盖章)Projectsupervisiondepartment(Chapter)总监理工程师(签字):Chiefengineerforconstructioninspection(Signature)YY年MM月DD日审批意见:Reviewcomments:总包单位(盖章)EPC(Chapter)专业工程师(签字):Professionalengineer(Signature)项目负责人(签字):ProjectLeader(Signature)YY年MM月DD日填报说明:本表一式3份,由分包单位填报,总包单位、项目监理部、分包单位各一份。PS:thisformwillbeprinted3copies,filledbycontractorunit,eachofEPC,projectsupervisioninstitutionandcontractorunithasonecopy.上海电力安装第二工程公司SHANGHAIPOWERERECTIONNO.2CO.作业指导书workinginstruction编号NO.:[SPESC]-FABS-QJ-016工程名称:泰国TPIPP150MW电厂工程Projectname:TPIPP150MWPOWERPLANT作业项目名称:四大管道施工方案Jobprojectname:Fourpipelineconstructionplan编制部门:汽机专业Compilingdepartment:Turbinespecialty编写Prepared:日期Date:审核Reviewed:日期Date:批准Approved:日期Date:出版日期DateofPublish版次EditionNo.第一版目录1工程概况.................................................................................................................................................................11.1工程概况......................................................................................................................................................11.2工程量..........................................................................................................................................................12编制依据.................................................................................................................................................................13工作量.....................................................................................................................................................................13.1主蒸汽管道..................................................................................................................................................13.2再热(热段)蒸汽管道安装......................................................................................................................13.3再热(冷段)蒸汽管道安装......................................................................................................................23.4高压给水管道安装......................................................................................................................................23.5主要工程量一览表......................................................................................................................................24参加作业人员资格和要求.....................................................................................................................................34.1作业人员的资格和要求.............................................................................................................................35作业所需的机具、工器具的规格和要求.............................................................................................................45.1作业所需的主要器具规格和要求.............................................................................................................46作业前应做的准备工作.........................................................................................................................................46.1施工准备....................................................................................................................................................46.2施工场地及工具应具备的条件................................................................................................................57作业程序、方法和工艺质量要求.........................................................................................................................57.1施工前准备..................................................................................................................................................57.2安装程序及步骤..........................................................................................................................................57.3阀门安装......................................................................................................................................................77.4支吊架安装..................................................................................................................................................77.5流量测量、节流装置安装..........................................................................................................................97.6疏、放水管道安装..........................................................
本文标题:四大管道施工方案审报版
链接地址:https://www.777doc.com/doc-4587514 .html