.密级检索号614-051004杭州意能电力技术有限公司技术文件华能玉环电厂4×1000MW机组工程#1、2机组输煤系统调试方案二00六年六月.华能玉环电厂4×1000MW机组工程#1、2机组输煤系统调试方案方案编写:杨冀明方案审核:潘国清方案批准:沈伟国.目录1前言············································································································12系统及设备主要技术规范············································································13调试前应具备的条件···················································································44调试工作程序及步骤···················································································55安全注意事项······························································································86组织分工及时间安排···················································································9附录:分系统危险源辨识、评价、控制实施表调试过程记录表清单调试质量控制实施情况表分系统调试前检查清单调试安全技术交底会记录单调试挡板、阀门动作试验记录单联锁保护试验记录单分系统试运行记录表分项调整试运质量检验评定表分部试运签证验收卡杭州意能电力技术有限公司华能玉环电厂4ⅹ1000MW机组工程#1、2机组输煤系统调试方案.1摘要本方案详细介绍了华能玉环电厂1000MW工程#1、2机组输煤系统调试的目的、方法、内容、步骤和标准,方案后附录包括了分系统调试检查清单、联锁试验记录表、质量验评表、试运行记录表等,为调试时参考及记录依据,以便于调试工作正常、有序地进行。关键词方案输煤系统调试玉环电厂1前言1.1目的为保障华能玉环发电厂4×1000MW工程#1、2机组输煤系统调试工作的顺利进行,特编写本技术方案。本方案用于指导输煤系统安装结束,完成设备单体调试后的分系统试运行工作,以确认输煤系统内各主辅设备安装正确无误,设备运行性能良好,控制系统工作正常,系统能满足机组整套启动需要。1.2调试说明1.2.1输煤系统调试从系统安装结束、单体调试完成后开始,包括辅助设备调试、联锁保护试验、驱动电机试转等项目。1.2.2为保证输煤系统试运行安全、可靠地进行,联锁保护试验安排在系统试运前进行,如因条件限制不能全部完成,部分不影响系统试运的项目可延后进行。1.2.3调试期间,系统内各设备的运行、操作应严格按照制造商有关说明及电厂的运行规程执行,以确保设备安全运行。1.3调试依据及标准输煤系统调试应严格遵循以下有关规程:1.3.1原《火力发电厂基本建设工程启动及竣工验收规程(1996年版)》。1.3.2原《电力建设施工及验收技术规范(1996年版)》。1.3.3《火电工程启动调试工作规定》。1.3.4原《火电工程调整试运质量检验及评定标准(1996年版)》。1.3.5原《电力建设施工及验收技术规范锅炉篇(1996年版)》。1.3.6原《火力发电厂运煤设计技术规定》(DLDJ1-93)(电力规划设计院)。1.3.7制造商《系统流程图》、《系统设计说明》。1.4调试质量标准:昀终调试质量验评合格率100%,优良率90%以上。2系统及设备主要规范2.1系统简介华能玉环发电厂4×1000MW工程#1、2机组输煤系统新建一座5万吨级专用卸煤码头,二台额定出力为1500t/h的桥式抓斗卸船机。由卸船机卸下的煤通过码头C-01A/B皮带机转运至引桥C-02B皮带机,送至厂内T-02转运站进入厂内输煤系统。燃煤进入T-02转运站后,经C-03B、C-04B皮带机及T-03、T-04转运站进入煤场或主厂房原煤仓。本期工程输煤系统设置二套筛碎设备,二台重型环锤式碎煤机、碎煤机前后共设三级电磁除铁器,分别在C-11A/B、C-13A/B、C-14A/B皮带机上。二台C-03A/B、二台C-14A/B皮带机电子皮带秤。在T-03转运站设有1套三级缩分、二级破碎入厂煤机械取样装置,在碎煤机室出口处设有1套二级缩分、一级破碎入炉煤机械取样装置。杭州意能电力技术有限公司华能玉环电厂4ⅹ1000MW机组工程#1、2机组输煤系统调试方案.2每台皮带机头部和导料槽处都配有收尘和喷雾装置。煤场采用旋转喷淋枪进行抑尘。本期工程输煤系统采用可编程器控制的方式。卸船机和斗轮机具有相对独立的控制操作功能,能与煤控室进行信息交换。当码头来煤时根据煤仓情况,可使部分煤进入煤仓,亦可进入贮煤场。当煤仓需要加料时,可使上煤皮带机单路或双路运行选一台或二台斗轮机工作。为确保皮带机的安全,每条皮带机均应配备以下安全装置:(1)速度开关,(2)跑偏开关,(3)打滑开关,(4)紧停拉绳开关,(5)防撕裂开关,(6)堵煤开关,(7)拉紧装置限位开关。其简要流程图如下:C-11B皮带机C-11B皮带机C-11A皮带机C-11A皮带机在#1、2机组的输煤系统的调试内容中,C-21A/B皮带机、T-21转运站、C-21A/B皮带机、C-22A/B皮带机、C-23A/B皮带机、C-20A/B斗轮机、T-23转运站、T-24转运、C-24皮带机、C-25A/B皮带机、C-26A/B皮带机、C-27A/B皮带机、C-28A/B皮带机、20AB碎煤机,先不参与调试。C-04A/B皮带机T-04转运站C12皮带机T-05转运站10A斗轮机C01A/B皮带卸煤码头C02A/B皮带机T-02转运站C-03A/B皮带机T-03转运站10B斗轮机T-11转运站T-06转运站C-13A/B皮带机碎煤机室C-14A/B皮带C-15A/B皮带机T-01转运站#1、#2炉原煤仓杭州意能电力技术有限公司华能玉环电厂4ⅹ1000MW机组工程#1、2机组输煤系统调试方案.32.2系统主要设备及技术规范输煤系统主要由下列设备组成:2.2.1皮带机系统:C-01A/B皮带机、C-02A/B皮带机、C-03A/B皮带机、C-04A/B皮带机、C-11A/B皮带机、C-12皮带机、C-13A/B皮带机、C-14A/B皮带机、C-15A/B皮带机。2.2.2筛分及破碎系统:滚轴筛、环锤式碎煤机、带式电磁除铁器、盘式电磁除铁器、入厂煤取样装置、入炉煤取样装置、电子皮带秤和循环链码装置。2.2.3煤场机械系统:悬臂斗轮堆取料机、轮式装载机和推煤机2.2.4水力清扫系统:地面冲洗装置、摇臂喷头、排污泵。皮带机技术规范详见表1,表2,表3:表1设备名称带宽(mm)带速(m/s)额定出力(t/h)C-01A/B皮带机18003.53600C-02A/B皮带机18003.53600C-03A/B皮带机18003.53000C-04A/B皮带机18003.53600C-11A皮带机18003.53600C-11B皮带机18003.53600C-12皮带机14002.51500C-13A/B皮带机14002.51500C-14A/B皮带机14002.51500C-15A/B皮带机14002.5150010A/B斗轮机18003.5堆料Q=3600取料Q=1500取样装置18003600电子皮带秤18003.53600循环链码称量范围:300-1500t/h,称量精度:0.5级称量范围:700-3600t/h,称量精度:0.25%称量范围:300-1500t/h,称量精度:0.25%电动三通挡板B=1400mm(4台),B=1800mm(2台),排污泵流量:50m3/h,扬程:0.25Mpa电机:Y160M-4,11KW,IP56表2电机主要技术规范设备名称制造厂家型号功率(kW)电压(V)C-01A/B皮带机湘潭电机厂YKK400S-44006000C-02A/B皮带机湘潭电机厂YKK4003-43156000C-03A/B皮带机湘潭电机厂YKK4004-43556000C04A/B皮带机湘潭电机厂YKK4003-43156000C-11A皮带机湘潭电机厂YKK4005-44006000杭州意能电力技术有限公司华能玉环电厂4ⅹ1000MW机组工程#1、2机组输煤系统调试方案.4C-11B皮带机湘潭电机厂YKK4005-44006000C12皮带机湘潭电机厂Y315L2-4180380C-13A/B皮带机湘潭电机厂Y3554-42×2506000C-14A/B皮带机湘潭电机厂YKK4002-42×2806000C-15A/B皮带机湘潭电机厂Y315M2-42×160380表3减速器主要技术规范:设备名称制造厂家型号(KW)传动比(i)C-01A/B皮带机德国FLENDERB3SH15B21.9C-02A/B皮带机德国FLENDERH2SH16B23.0C-03A/B皮带机德国FLENDERH2SH1422.4C-04A/B皮带机德国FLENDERH2SH1322.4C-11A皮带机德国FLENDERH2SH1422.4C-11B皮带机德国FLENDERH2SH1422.4C12皮带机德国FLENDERH2SH1131.5C13A/B皮带机德国FLENDERH2SH1131.5C14A/B皮带机德国FLENDERH2SH1431.5C15A/B皮带机德国FLENDERH2SH1131.5滚轴筛主要技术规范见表4,表4滚轴筛主要技术规范额定出力(t/h)入料粒度(mm)出料粒度(mm)电机功率(kW)型号1500≤300≤302.2×12XGS1812B环锤式破碎机主要技术规范见表5表5环锤式破碎机主要技术规范出力(t/h)入料粒度(mm)出料粒度(mm)电机功率(kW)型号1000≤350≤25560HCSC103分系统调试前应具备的条件3.1输煤系统所有辅机安装结束,相关仪控设备及电气设备安装、校验完毕,经静态验收合格,并提供相关仪控、电气设备定值汇总。3.2输煤系统各单体试验结束,已确认运行状况良好,参数正常,CRT状态显示正确。3.3动力电源、控制电源准备就绪。3.4确认驱动电机均能用手光滑盘转。3.5系统调试组织和监督机构已成立,并开始有序地开展工作。杭州意能电力技术有限公司华能玉环电厂4ⅹ1000MW机组工程#1、2机组输煤系统调试方案.53.6调试资料、工具、仪表、记录表格已准备好。3.7试运现场已清理干净,安全、照明和通讯措施已落实。3.8仪控、电气专业有关调试结束,配合机务调试人员到场。3.9消防设施具全。4调试内容及步骤4.1调试程序图4.2辅助设备调试试运4.2.1输煤系统各热工测点正确无误。4.2.2输煤系统煤泥浆输送管路已经过打压试验合格。4.3联锁保护及报警试验确认4.3.1皮带机联锁确认试验。4.3.2滚轴筛联锁确认试验。4.3.3报警确认试验4.4输煤系统内各分系统试运试验4.4.1皮带机试运。4.4.2滚轴筛试运。4.4.3环锤式碎煤机试运。4.4.4悬臂斗轮堆取料机试运。主设备安装结束仪控设备安装结束电气设备安装结束管道、阀门安装结束安全条件满足联锁保护试验报警试验辅助设备调试联锁保护及报警试验调试须满足的条件确认皮带机试转各分系统投运及其调整杭州意能电力技术有限公司华能玉环电厂4ⅹ1000MW机组工程#1、2机组输煤系统调试方案.64.4.5取样装置试运。4.4.6实物校验装置试运4.5输煤系统试运行输煤系统投运前检查、确认以下条件满足,见表4:表4序号项目备注1各紧固件无松动现象2各润滑部位按规定加注足够的润滑油3系统内所
本文标题:输煤系统调试方案
链接地址:https://www.777doc.com/doc-6229195 .html