施工方案********工程脚手架安全专项施工方案批准:审核:编制:二O一一年四月********工程脚手架安全专项施工方案—1—目录1.工程概况·····································································21.1工程概况1.2施工平面布置1.3施工要求1.4安全保障体系1.5现场条件2.编制依据·····································································33.材料及人员计划····························································43.1材料选择3.2人员计划4.工艺流程·····································································74.1施工工艺4.2施工方法5.检查验收······································································86.施工安全保证措施···························································96.1组织保障6.2安全保障技术措施6.3安全管理措施6.4外脚手架安全措施6.5“三宝”“四口”“五临边”的防护措施6.6架子工严把“九道关”6.7脚手架安全使用教育关7.应急预案·······································································167.1目的7.2应急领导小组及其职责7.3应急反应预案8.预防与预警··································································18********工程脚手架安全专项施工方案—2—1.工程概况1.1工程概况********工程地下一层,裙房三层,主楼九层。总建筑面积42300.59㎡,±0.000标高相当于绝对高程76.7m,其中地上31945.51㎡,地下10355.08㎡。基础埋深6.1m,地下室主要为车库、设备机房及相关辅助用房,建筑物总高度为38.45米。其中地下室高度为5.1米,一层层高为6米,二层为5.4米,三至八层层高均为3.8米,九层层高3.85米。1.2施工平面布置见附图二1.3施工要求1.3.1确保脚手架、卸料平台在使用周期内安全、稳定、牢固。1.3.2脚手架、卸料平台在搭设及拆除过程中要符合工程施工进度要求,操作人员需取得特殊作业人员资格上岗证、持证上岗,人证相符。1.4安全保障体系1.5现场条件1.5.1现场1-5层采用落地式脚手架,5-9层采用悬挑式脚手架,由于结构复********工程脚手架安全专项施工方案—3—杂,各个部位脚手架搭设方式不同,具体搭设方式详见外脚手架施工方案1.5.2由于工程现场地处山洼处,雨后容易局部存水,所以现场在搭设脚手架时要在外架四周设置排水沟,防止积水。1.5.3遇局部场地不平整的部位,在搭设前,必须将不平整位置整平、夯实,然后方可搭设。2.编制依据《建筑结构荷载规范》GB50009-2001《混凝土结构设计规范》GB50010-2002《钢结构设计规范》GB50017-2003《建筑施工安全检查标准》JGJ59-99《建筑施工高处作业安全技术规范》JGJ80-91《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-20013.材料及人员计划3.1材料选择3.1.1钢管脚手架钢管应采用现行国家标准《直缝电焊钢管》(GB/T12793)或《低压流体输送用焊接钢管》(GB/T3092)中规定的3号普通钢管,其质量应符合现行国家标准《碳素结构钢》(GB/T700)中Q235-A级钢的规定。脚手架钢管采用φ48×3.5钢管。钢管的尺寸和表面质量应符合下列规定:新钢管:应有产品质量合格证;应有质量检验报告,钢管材质检验方法应符合现行国家标准《金属拉伸试验方法》(GB/T228)的有关规定,质量应符合本规范第3.1.1条的规定;钢管表面应平直光滑,不应有裂缝、结疤、分层、错位、硬弯、毛刺、压痕和深的划道;钢管外径、壁厚、端面等的偏差,应符合规范规定;钢管必须涂有防锈漆。旧钢管:表面锈蚀深度应在规范规定范围以内,锈蚀检查应每年一次。检查时,应********工程脚手架安全专项施工方案—4—在锈蚀严重的钢管中抽取三根,在每根锈蚀严重的部位横向截断取样检查,当锈蚀深度超过规定值时不得使用;3.1.2扣件扣件式钢管脚手架应采用可锻铸铁制作的扣件,其材质应符合现行国家标准《钢管脚手架扣件》(GB15831)的规定;采用其它材料制作的扣件,应经试验证明其质量符合该标准的规定后方可使用。脚手架采用的扣件,在螺栓拧紧扭力矩达65N·m时,不得发生破坏。3.1.3脚手板脚手板可采用钢、木、竹材料制作,每块质量不宜大于30kg,现场采用普通木架板,其材质应符合现行国家标准《木结构设计规范》(GBJ5)中Ⅱ级材质的规定。脚手板厚度不应小于50mm,两端应各设直径为4mm的镀锌钢丝箍两道。3.1.4连墙件连墙杆的材质应符合现行国家标准《碳素结构钢》(GB/T700)中Q235-A级钢的规定。3.2人员计划3.2.1专职安全生产管理人员:4人3.2.2特种作业人员:12人4.工艺流程4.1施工工艺4.1.1落地式脚手架:准备工作→立杆底座→立杆→横杆→剪刀撑→接头锁紧→安装连墙件→铺设脚手板→立挂安全网→上层立杆→立杆连接→横杆4.1.2悬挑式脚手架:准备工作→悬挑型钢的架设→立杆→横杆→剪刀撑→接头锁紧→安装连墙件→铺设脚手板→立挂安全网→上层立杆→立杆连接→横杆4.1.3脚手架拆除工艺密目网→横杆→立杆→剪刀撑→连墙件4.1.4工艺参数********工程脚手架安全专项施工方案—5—普通型钢悬挑脚手架脚手架排数双排大小横杆布置小横杆在上搭设高度(m)20立杆型号48*3.5立杆纵距(m)1.5立杆横距(m)1.05立杆步距(m)1.8连墙件布置方式两部三跨型钢悬挑长度(m)1.5锚固长度(m)3钢丝绳支撑道数1施工均布荷载(KN/m2)3同时施工层数2脚手板铺设层数2地区青岛市崂山区基本风压(KN/m2)0.354.2施工方法4.2.1脚手架基础本工程±0.000标高以下落地式双排脚手架全部坐落于基础土层上,±0.000标高以上落地式双排脚手架全部坐落于一层楼板上。脚手架立杆设钢底座,底座下为截面大于150×150×3垫板焊接20mm钢筋、木垫板,底座和垫板应准确地放在立杆的定位线上。4.2.2悬挑型钢的支设悬挑结构为16#工字钢和Φ14斜拉钢丝绳。用预埋在楼板中的Φ18mmΩ型圆钢环将工字钢卡住,并用硬木楔将工字钢楔紧;在工字钢端部焊一Φ25mm钢筋与14#钢丝绳连接,钢丝绳上端与上层梁中预埋的Φ16吊环连接,通过斜拉可减少悬挑工字钢的挠度。在外挑工字钢上(与立杆对应位置处)焊2根Φ25mm、高100mm的钢筋,以固定立杆。型钢悬挑示意如下:48钢管16#工字钢一Φ16预埋钢筋Φ14钢丝绳Φ25焊接悬挑架大样一预埋Φ16钢筋拉钩Φ25钢筋Φ25钢筋详图2详图118#花篮拉杆********工程脚手架安全专项施工方案—6—4.2.3脚手架搭设立杆、大横杆、小横杆等杆件间距除符合下述要求外,还应满足规范要求,遇柱墙需要加大间距时,应按规范要求进行加固。(1)脚手架钢管的搭设外脚手架采用双排Φ48×3.5mm钢管搭设,立杆的横距0.9m、纵距1.5m、横杆的步距1.8m、内立杆离墙350mm(为保证模板的安拆空间)。脚手架立面示意图1800×8密目安全网脚手板楼板预留钢管拉结钢丝绳栏杆扫地杆抱柱拉结Φ14mmΩ型圆钢环1500×8扫地杆木垫板钢底座脚手架剖面示意图********工程脚手架安全专项施工方案—7—脚手架必须设置纵、横向扫地杆。纵向扫地杆应采用直角扣件固定在距底座上皮不大于200mm处的立杆上。横向扫地杆用直角扣件固定在紧靠纵向扫地杆下方的立杆上。立杆与大横杆的交点处设置小横杆,小横杆应紧靠立杆用扣件与大横杆扣牢。在脚手架高度和长度方向连续设置剪刀撑,以增强脚手架的整体刚度。每组剪刀撑跨越不小于5根立杆;剪刀撑钢管的搭接长度不小于1m,用3个扣件固定搭接钢管;剪刀撑与横向水平杆的伸出端或立杆相交处应用旋转扣件固定。(2)连墙件的设置本工程连墙件为刚性连接,按二步三跨设置,其位置宜靠近主节点,偏离主节点的距离不应大于300mm。连墙件采用在楼板上预埋Φ48×3.5mm钢管,其长度500mm,将拉结杆与此预埋钢管连接固定。(3)脚手板的搭设本工程除悬挑层采用木板脚手板,每一悬挑单元设一作业层,并将该单元底层满铺脚手板作为防护层,防护网应铺满内立杆与混凝土墙之间0.35m的空间,作业层设防护栏杆和挡脚板。挡脚板:200mm高,图条的倾角45度,材料为厚15mm的木板,设置在凡是铺设脚手板的作业层及斜道两侧。详细做法见下图:铺设脚手板时,在两立杆间加二根纵向横杆并与横向水平杆连接,小横杆应在大横杆的下面。作业层脚手板要铺满、铺稳,离开墙面150mm。脚手板应按竖向间距每12m铺设一层。(4)密目网的设置脚手架使用密目安全网全封闭。密目网设置在外排立杆的内侧,用尼龙挡脚板的做法楼板、梁预埋拉接点设置方式楼板48钢管(预埋,长500********工程脚手架安全专项施工方案—8—绳将密目网之间绑扎,并每隔250mm与脚手架环扣系牢。(5)斜道的搭设:斜道附着脚手架设置,坡度为1:3,拐弯处设平台,斜道和平台按临边防护要求设1.2m高的防护栏及挡脚板;斜道采用20~30mm厚脚手板,板面上每隔250mm~300mm设置1根防滑木条。(6)安全平网设置:脚手架首层底部处应设置首层安全平网,每隔不大于10m再设层间安全平网。安全平网内侧距墙体不应大于15cm,大于时应加设安全平网进行有效防护。(7)防护栏杆设置:在操作层上,脚手架外侧大横杆与脚手板之间要按要求设置两道防护栏杆,上栏杆高度为1.2m,下栏杆高度0.6m。,5.检查验收脚手架及其地基基础应按规范规定的时间阶段和内容进行检查与验收。其主要验收标准规定如下:(1)构架尺寸符合规范及设计要求,个别部位的尺寸变化应在允许的调整范围之内。(2)节点的连接可靠,扣件的拧紧程度应控制在拧力矩达到40~60N·m。(3)脚手架立杆的垂直度偏差应≤1/300,且应同时控制其最大垂直度偏差值:当架高≤20m时为不大于50mm;当架高>20m时为不大于75mm。(4)纵向钢平杆的水平偏差应≤1/250,且全架长的水平偏差值应不大于50mm。(5)作业层铺板、安全防护措施等均应符合施工设计和规范要求。高度在20m以内的脚手架由专职安全员组织验收,高度大于20m时,由项目技术负责人汇通安全员组织验收,验收标准按照规范JGJ130-2001执行。6.施工安全保证措施6.1组织保障6.1.1安全保证体系见附图26.1.2环境保证体系********工程脚手架安全专项施工方案—9—6.2安全保障技术措施脚手架安装:(1)避雷装置应包括接闪器、引下线和接地装置。1)房屋四角的脚手架立杆上设置接闪器,接闪器用直径25-32mm,壁厚不小于3mm的钢管或直径不小于12mm的钢筋制作,设在脚手架易遭受雷击的顶端。高度不小于1m,并将所有最上层的横杆全部连通,形成避雷网路。2)引下线应采用直径不小于8mm的圆钢制作。3)垂直接地体宜采用长为2.5m直径12mm圆钢制作,间距5m设置。水平********工程脚手架安全专项施工方案—10—接地体宜采用12mm圆钢或4mm扁铁制作。4)接地体埋深不小于0.6m,应避开人经常活动区。避雷装置的引线、接地连接线等连接必须采用焊接形式,焊接长度为圆钢直径的6倍。(2)外脚手架不得搭设在距离外架空线路德安全距
本文标题:脚手架安全专项方案
链接地址:https://www.777doc.com/doc-1268747 .html