您好,欢迎访问三七文档
当前位置:首页 > 建筑/环境 > 工程监理 > X年北京奥运射击馆文件(施工组织设计)-3版
北京射击馆金属屋面工程资格赛馆施工组织设计****建设工程有限公司二零零五年十二月一日2****建设工程有限公司报审手续报审文件名称北京射击馆金属屋面工程资格赛馆施工组织设计编辑人报审人报审时间质量部门审批意见:负责人签字:日期:安全部门审批意见:负责人签字:日期:技术部门审批意见:负责人签字:日期:3目录索引一、工程概况··································································第6页二、编制依据··································································第6-7页三、施工图深化设计的完善确认安排、材料确认安排·············第7-10页3.1施工图二次深化设计的安排计划···································第7页3.2材料供应计划···························································第7-10页四、主要施工方案·························································第10-21页4.1施工前的必要准备工作···············································第10-12页4.2施工前对钢结构的复检验收·········································第12-13页4.3资格赛馆B区屋面系统施工安装计划·····························第13-15页4.4资格赛馆A区屋面系统施工安装计划····························第16-18页4.5资格赛馆檐口封板施工安装计划···································第18-19页4.6资格赛馆檐口百叶施工安装计划···································第19页4.7资格赛馆北立面立窗施工安装计划································第19页4.8资格赛馆受弹区采光天窗、成品固定窗阳光板施工安装计划·······································································第19-20页4.9资格赛馆铝板饰面格栅施工安装计划·····························第20页4.10资格赛馆挡弹板雨篷施工安装计划·······························第20页4.11资格赛馆虹吸排水系统施工安装计划····························第20-21页44.12资格赛馆屋面避雷系统施工安装计划····························第21页4.13资格赛馆自动开启天窗施工安装计划····························第21页4.14资格赛馆屋面系统清理、自检、报验····························第21页4.15现场施工平面布置图················································第21页五、水电施工方案介绍···················································第22-23页5.1对射击馆水电施工情况简介·········································第22-22页5.2施工程序和方案························································第23页六、工程投入的主要物资和施工机械设备情况、主要施工机械进场计划(屋面板加工及安装机械设备能力)·····················第23-29页6.1工程投入的主要施工机械设备情况·······························第23-29页6.2主要施工机械进场计划··············································第29页七、劳动力安排计划······················································第30页八、确保工程质量的技术组织措施····································第31-41页8.1质量目标································································第31页8.2确保工程质量的技术组织措施·····································第31-41页九、施工安全保证措施···················································第41-52页9.1安全生产管理目标····················································第41页59.2安全员岗位责任制····················································第41-42页9.3现场安全管理··························································第42-45页9.4安全管理规定···························································第45-47页9.5用电安全措施··························································第47页9.6手持电动工具操作安全注意事项···································第48-49页9.7脚手架搭设·····························································第49页9.8安全技术交底制度·····················································第49-50页9.9全生产教育制度························································第50-51页9.10高处坠落事故预防措施·············································第51-52页十、确保文明施工的技术组织措施····································第52-54页十一、施工进度计划及保证措施·······································第54-57页11.1工期计划································································第54页11.2施工进度计划横道图·················································第54-55页11.3确保工期的技术组织措施··········································第55-57页十二、施工组织设计应附表格及图····································第58-69页6施工组织设计一、工程概况:北京射击馆资格赛馆为3-4层建筑,金属屋面工程是一个较复杂的、集多种功能用途於一体的屋面系统。它包括了屋面最基本功能:防水保温,还有采光功能、消防排烟功能、吸音功能、虹吸排水功能等。将多种功能的设计、制作融为一体。资格赛馆屋面造型呈单坡高低跨形式,柱间距最大为8.4米,屋面上还分别设有独立式的屋顶玻璃天窗及玻璃采光带,有效地使用自然光。并在檐口部位设有铝合金遮阳百叶。在南立面上设计了独特造型的檐口,在东西立面特别设计了视觉美观的弧形檐口,北立面则设有铝板饰面隔栅,增加了整体建筑的可观性。二、编制依据本施工方案编制依据为:2.1《2008年奥运会北京射击馆金属屋面工程招标文件》2.2《2008年奥运会北京射击馆金属屋面工程有关答疑文件》2.3施工及工程相关用图纸。2.4参照的部分标准和施工规范:2.4.1建筑及结构设计规范2.4.1.1《民用建筑设计通则》JGJ37-872.4.1.2《建筑防雷设计规范》GB50057-942.4.1.3《屋面工程设计规范》BG5020772.4.1.4《建筑设计防火规范》GB16-87(修订版)2.4.1.5《建筑结构荷载规范》GBJ9-872.4.2工程技术规范:2.4.2.1《压型金属板设计施工规范》YBJ2162.4.2.2《金属屋面系统的设计和安装规范》AS15622.4.2.3《建筑幕墙》JG3035-962.4.2.4《玻璃幕墙工程技术规范》JGJ102-962.4.2.5《钢结构工程施工及验收规范》GB50205-952.4.2.6《国际计量标准》ST标准三、施工图深化设计的完善确认安排、材料确认安排:3.1施工图二次深化设计的安排计划:我公司首先进行内部技术交底,将公司总部、生产企业内部及技术部的设计工作协调及时安排好。从9月20日起我公司技术负责人先后几次与设计院进行深化设计交底工作,十一假期又加班加点绘制射击馆屋面深化设计图纸,全套设计方案图纸已全部完成并送交设计院审核汇签。至目前部分屋面及排水系统的图纸已签回。3.2材料供应计划:材料是保证施工顺利进行的物质基础,这些物资准备工作在射击馆资格赛馆金属屋面工程开工之前已大部分完成。根据各种材料的需要量计划,分别落实货源,安排运输和储备,可完全满足连续施工的要求。83.2.1各项材料供应计划:3.2.1.1钢结构件:钢结构支承件是安装初期使用的材料。此项材料已安排在我公司国内工厂进行预制,并做好表面除锈及热镀锌处理后运抵施工现场,自11月中旬资格赛馆B区屋面各部位钢结构材料陆续运抵现场。3.2.1.2彩色压型钢底板:屋面彩色钢底板采用国内知名企业生产的彩色薄钢板卷材,在我公司国内工厂压型,于11月中旬开始陆续运抵现场,保证底板的铺装顺序进行。3.2.1.3屋面面板支撑:“铝合金屋面系统”采用的面板支撑为高强铝合金支架,本项材料为我公司常规产品,在我工厂内有大量储备,届时将随压型钢底板同时发运至工地,以满足安装需要。“镀铝锌彩色钢板屋面系统”专用的面板支架,亦为我公司常用材料,我公司工厂常年备有大量库存,可随压型钢底板一并发往工地进行安装。3.2.1.4保温棉:由于保温棉的体积大、重量轻,不易于现场保存,根据安装进度计划,我公司于是12月初安排在距离北京较近的玻璃棉制品厂生产备货,届时依现场实际铺装进度,各阶段安装需用数量,随时汽运往工地。3.2.1.5屋面面板材料:“铝合金屋面系统”屋面面板材料采用金属银灰色铝、锰、镁合金板,此项材料我公司国内工厂长年备有大量进口现货库存,可随时满足射击馆金属屋面工程的安装需求,预计于是12月中旬随面板压型机同期运往施工9现场。“镀铝锌彩色钢板屋面系统”屋面面板材料采用国内知名企业上海宝钢集团生产的镀铝锌彩色薄钢板,在屋面面板开始安装前10天可将钢卷材和专用的压型设备同时运至施工现场进行加工。3.2.1.6采光天窗玻璃:资格赛馆和决赛馆使用的钢化中空夹胶玻璃,属易碎品,不易提早在现场存放。采光天窗钢结构工序于是12月中旬陆续开始焊接时,我公司即依玻璃分格尺寸进行测量,并安排玻璃订货生产,10天可将成品玻璃生产完成并运至施工现场。3.2.1.7采光天窗聚碳酸酯板:
本文标题:X年北京奥运射击馆文件(施工组织设计)-3版
链接地址:https://www.777doc.com/doc-165512 .html