张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)桩基工程施工方案北京城建四建设工程有限责任公司张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)1编制:审核:审批:张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)2目录一、工程概况············································································3二、编制依据············································································4三、施工条件············································································4四、静力压桩机对周围环境环保的影响及防护措施····························4五、施工方法············································································61、施工准备············································································62、施工放样············································································73、沉桩顺序及工艺流程·····························································84、沉桩质量控制······································································9六、工程质量保证措施、质量认证体系·········································12七、安全技术组织措施······························································13八、文明施工管理措施······························································14九、施工进度计划及施工主要机械设备配备···································14十、施工技术组织措施······························································16张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)3一、工程概况1、工程名称:张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)2、工程地点:张江镇C-6-1、C-4-23、建设单位:上海鼎汇房地产开发有限公司4、设计单位:上海电子工程设计研究院有限公司5、监理单位:上海振南工程咨询监理有限责任公司6、勘察单位:浙江省工程勘察院上海分院7、施工单位:北京城建四建设工程有限责任公司8、桩形:PHC-AB400-30m、PHC-AB300-24m、砼方桩(0.3)2×22m工程名称桩体类型桩长(m)桩顶标高(m)桩数单桩竖向承载力(KN)±0.000绝对标高(m)极限承载力标准值特征值T3-T4住宅楼各252套PHC-AB40030-4.40504130020805.4T5-T6住宅楼各170套PHC-AB40030-4.40340130020805.4T7住宅楼PHC-AB40030-4.40340130020805.4B1别墅PHC-AB30024-3.55814106565.3B2别墅PHC-AB30024-3.55684106565.3B3别墅PHC-AB30024-3.55874106565.3B4别墅PHC-AB30024-3.55834106565.3B5别墅PHC-AB30024-3.55914106565.3B6别墅PHC-AB30024-3.55614106565.3B7别墅PHC-AB30024-3.55654106565.3GB1别墅PHC-AB30024-4.231524306885.3GB2别墅PHC-AB30022-5.6051844407044.852号地下车库及会所(0.3)222.45-5.55987抗拔设计值300抗拔极限值5605.3注:1、PHC-AB400-30m配桩长度分别为11+7+12;2、其他工程桩均为两节均分;3、车库及会所正负零绝对标高有待设计确认(5.4);4、别墅数据仅作参考,待正式施工蓝图下发后校正。张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)49、现场北临丹桂路,西临青桐路地下管线离施工现场较近,其他为开阔地。二、编制依据1、浙江省工程勘察院上海分院《项目岩土工程勘察报告书》;2、张江镇3/2、3/3、3/7号地块住宅项目一期桩基工程桩位图;3、《建筑地基基础工程施工质量验收规范》(GB50202-2002);4、施工现场场地实际情况;5、国家及上海市颁布的安全操作规程及文明施工规定;6、上海市建筑标准设计图集《先张法预应力混凝土管桩》(DBJT08-92-2000)三、施工条件1、施工现场部分“三通一平”,继续完善中。2、地理位置:张江镇丹桂路南侧,申江路西侧,青桐路东侧。3、地形地貌:本场地大部分地段为农田,地貌类型属河沼平原,中间有正式道路,周围有道路、河流和桥。4、供电情况:现场有配电箱,能提供桩机使用用电四、静力压桩机对周围环境环保的影响及防护措施静力压桩与锤击桩相比具有无噪音、无震动、无污染、安全文明等优张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)5点,但是在载饱和软粘土地区打压桩,会产生超静空隙水,由于其消散慢,会产生累计叠加,波及邻近范围的土地隆起和水平位移,对其范围内的建筑物、管线产生不利影响,一方面通过监测和调整压桩顺序进行防护,另方面为确保在打压桩期间及基坑开挖期间周围土地、建筑物、管线不受影响,将在打压桩期间采用应力释放孔减少土体挤压。在各种打压桩防护措施中,最为经济实用的措施是合理安排沉桩顺序及沉桩速度,先将离保护对象最近的桩打压完,形成封闭桩,其余的打压桩方向原则上是向背离被保护对象方向进行。1、对于本工程,北侧临路,其他方向均为开阔地,且北侧边桩离围墙几近20m、桩设计密度不大,故本工程不考虑设置防挤孔及砂井,只辅以适量排水沟兼做防挤沟,现场已做好部分排水沟,施工时可视情况增设。2、施工顺序的原则:东西迂回,由北向南。3、环境监测措施委托有关专业单位对周围需要保护的管网及建筑物进行设点观测。监测方案,观测点及观测方法等在打压桩施工前完成,根据监测资料反映的数据,必要时调整沉桩速度,做到信息化施工。4、防挤沟内的排水措施挤沟内的水,排入集水井内,每隔70米设一集水井,集水井内的水经沉淀后用潜水泵排入市政下水管网(东北侧许可使用的污水排放井)。张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)6五、施工方法1、施工准备1.1、场地填压实,满足负荷重的桩机正常运行,若遇暗浜时影响正常施工,清除淤泥后,回填建筑垃圾或三合土,并压实。若深度超过基底标高,待地基验槽后挖出回填物,根据勘察单位意见进行处理。若遇多雨天气,边施工边处理(挖除表面淤泥,填以建筑垃圾),以保证施工质量为前提。1.2、在拟建建筑物周围铺设临时道路便于车辆运输。1.3、施工用电应满足3台桩机共300KW同时作业,作业区域配足照明设施,以便夜间施工,但灯光避免直射北侧及西侧居民楼。1.4、边桩周围建筑物(包括临时设施)的距离应大于4米。1.5、施工前清除地下、空间障碍物,如旧基础、防空洞、场地内原有地下管线等。施工场地周围做到排水畅通。1.6、主要机械设备调试正常、安全进场。见表1机械名称调试检查主要内容备注打桩机液压系统、电路系统、关键结构电焊机防护罩、电源、接地、接零装置注:桩机须挂牌后方可使用1.7、测量仪器及其校核。见表2张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)79、测量仪器检测合格报告另报1.8、桩的验收、起吊、搬运、堆放1.9、桩进行场外委托制作,进场卸车时应由建设单位、监理单位、施工等单位共同验收。验收依据:《建筑地基基础工程施工质量验收规范》(GB50202-2002);上海市建筑标准设计图集《先张法预应力混凝土管桩》(DBJT08-92-2000)的有关规定执行,如发现不合格桩或断桩,现场严格禁止使用。1.10、预制桩的质量要求:1.10.1预制桩的原材及施工质量严格按照《建筑地基基础工程施工质量验收规范》(GB50202-2002)执行。1.11、预制桩达到设计强度的100%方可起吊,桩在起吊和搬用时,必须做到平衡并不得损坏,水平调运时,吊点距桩端0.297L(L为桩长),单点起吊时,吊点距桩端0.293L。1.12、桩的堆放场地做到平整坚实,不得产生不均匀沉陷,堆放层数不得超过四层,不同规格的桩应分别堆放。2、施工放样2.1、施放建筑物主轴线,据此及桩位平面图测放桩位,经监理验收合仪器名称校核内容证书编号水准仪光学系统、调平装置等200002-3141经纬仪光学系统、调平装置等200201-0276钢尺热变形特性、刻度、精度等200212-0216压力表精确度、抗震性能等200010-1120张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)8格后方可打压桩。2.2、为了便于在施工过程中或验收时核对轴线及桩位,南侧在主轴线的延长线上距边桩20米以外设控制桩,北侧投设于围墙上。2.3、桩位定位前检查各轴线交点的距离是否与桩位图相符,无误后用直角坐标法或极坐标法测放样桩。样桩用木桩或钢筋标记,涂刷红漆便于寻找。打桩机就位后应对样桩进行复核,无误后再对中、打压桩。2.4、样桩轴线的允许偏差不得超过下列数值:单排桩10㎜,群桩20㎜。2.5、为了便于控制桩顶标高,在打压桩范围60m外引测两个以上水准控制点,经过监理的复核,验收合格后才能使用,并在施工过程中加以保护。本工程水准点采用测绘院给测绘成果中CT1。3、沉桩顺序及工艺流程3.1、沉桩顺序:为尽量减少对丹桂路向马路及地下管线的影响,原则为东西迂回,由北向南,即T3→T4→车库→T5→T6→T7,别墅也遵循此原则。3.2、工艺流程:验桩→吊桩→调平机身→对点位→压下桩→接桩→压上桩→送桩→记录(详见“压桩施工工艺流程图”)。3.3、压桩时各个工序应连续进行,尽量减少接桩焊接时间,严禁中途停止,造成沉桩困难。3.4、遇到下列情况应暂停压桩,并与设计、监理及业主方研究处理后继续施工。3.4.1、在初压时,桩身较大幅度的位移或倾斜;3.4.2、在打桩过程中,桩突然下沉或倾斜;张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)93.4.3、桩身破裂或压桩阻力突变;3.4.4、桩位位移较多或标高超限较大。压桩施工工艺流程图4、沉桩质量控制4.1、桩位控制:桩位偏差和垂直度应符合GB50202-2002规范要求,管桩查合格证外观检查判定控制网建立测放桩位桩机就位复核桩位对点OK桩尖插入打压上桩电焊接桩打压进入下一工序送桩进入下一工序张江集镇4街坊3/2、3/7丘和3街坊3/3丘宗地块项目(一期)10见表3表3序号项目允许偏差mm1上面盖有基础梁的柱:垂直基础梁的中心线延基础梁的中心线100+0.01H150+0.01H2桩数为1~3根或单排桩基中的桩1003桩数为4~16根桩基中的桩1/2桩径或边长4桩数大于16根桩基中的桩:最外边的桩中间的桩1/3桩径或边长1/2个桩径或边长注:H为施工现场地面标高与桩顶标高的距离4.2、影响桩位偏移和垂直度的因素很多,在施工中应注意以下几个方面
本文标题:桩基施工方案(广兰路桩基)
链接地址:https://www.777doc.com/doc-196002 .html