伊金霍洛旗影院无粘结预应力梁施工方案编制人:审核人:审定人:北京清控水木建筑工程有限公司2011年8月2目录一、工程概况························································································3二、施工组织安排和进度计划···································································32·1预应力分包施工内容范围:······························································32·2总包单位配合内容··········································································32·3施工人员配置················································································42.4工期与进度···················································································42.5劳动力安排计划·············································································42.6施工机械设备情况··········································································4三、工程所用材料··················································································5四、无粘结预应力施工工艺······································································64.1无粘结预应力大梁施工工艺流程························································64.2铺放前的准备工作··········································································64.3穿预应力筋···················································································74.4浇筑混凝土···················································································74.5预应力筋的张拉·············································································7五、质量保证体系··················································································8六、安全文明施工及环保要求···································································9七、竣工资料······················································································103一、工程概况伊金霍洛旗影院三层顶24到25轴之间设有无粘结预应力梁。本工程预应力采用了无粘结预应力。全部预应力钢筋采用1860级直径15.2mm的低松弛钢绞线,其标准强度fptk=1860N/mm2,设计张拉控制应力为75%fptk即1395Mpa。预应力筋锚固端采用挤压锚具,张拉端锚具单孔锚。所有预应力筋张拉端可设在柱后、板面或者梁侧,无论何种形式,竣工时所有预应力筋的张拉端锚具均应埋在混凝土内,不外露。二、施工组织安排和进度计划2·1预应力分包施工内容范围:1.提供预应力成套技术的施工组织设计等。2.提供预应力成套技术所需的预应力筋、锚具及相应配件,根据预应力施工组织设计进行预应力筋及专用马凳的加工制作,并且负责运至施工现场。3.负责预应力筋的铺放、张拉端节点的安装并负责预应力筋的张拉。4.进行预应力分项施工的质量监督和检查验收、服从监理公司的监督管理。5.预应力筋及锚具应符合《预应力混凝土用钢绞线》(GB/T5224-2003)、《预应力筋用锚具、夹具和连接器(GB/T14370-2000)》等有关规定。6.严格按设计图纸、相关规范与规程进行预应力施工,在不同施工阶段提供相应技术资料,并在结构验收时将各种预应力资料整理齐全,报总包、监理公司。2·2总包单位配合内容1.提供预应力部分的图纸、张拉前混凝土强度试验报告、和施工进度计划(指与预应力有关结构部分的支模、绑扎钢筋、浇混凝土的时间安排)。2.提供现场办公用房和机具存放库房一间。3.负责解决预应力筋张拉用操作平台和张拉设备用电源(380V、15A),能承担现场最大2台750W张拉千斤顶油泵的用电负荷。操作平台可以利用原有的脚手架,有必要的安全防护措施,应保证在预应力张拉端后1米范围内没有影响张拉的障碍物,张拉工人有足够摆放机具及张拉操作空间。4.提供施工现场预应力材料的装卸、下料和临时堆放的场地。5.在模板的制作和安装时应根据预应力施工组织设计的要求进行,以满足预应力施工工艺的要求。6.根据预应力施工组织设计进行预应力筋张拉后张拉端的混凝土封堵。7.负责协调安排好各工序、工种间的关系。48.在预应力部位支模前三天通知预应力筋进场铺放,准备张拉前三天通知进场张拉,张拉前一天提供张拉部位混凝土强度报告单。2·3施工人员配置预应力施工人员由技术负责人、施工工长、质检员、安全员及材料员组成。其中管理人员比例不低于总人数的10%,工程师都具有4年以上的预应力空心板施工经验;施工工长具有3年以上的预应力空心板施工经验,施工作业人员全部经过严格的岗位培训,60%以上的工人至少从事空心板施工工作2年以上。各职能分配如下:技术负责人:制定施工技术方案、进行技术交底,并负责质量控制、验收。施工工长:负责具体组织施工工作。质检员:负责施工质量检查、监督、验收工作。材料员:负责现场材料收发、清点、存放及技术档案保管。施工员:根据设计图纸,进行空心板的具体施工。2.4工期与进度根据总体的工期与进度计划来安排生产,同时根据现场的实际情况及时作出调整。保证施工需要的人员能随时到位,材料供应充足,计划投入的设备完好率100%。所有预应力筋、锚具及配件、均按照图纸具体要求前加工组装。进度上做到与总体施工进度相一致,力争做到预应力材料与轻质管随运随铺放,既不耽误工期又不致造成过多的积压占用场地。预应力的施工做到在保证质量前提下,与同层的钢筋工程和水电工程同步穿插进行,尽量少占工期。要保证预应力筋、锚具、承压板、螺旋筋、轻质管等材料供应充足、及时。预应力筋铺放不拖工期,不耽误混凝土的正常浇筑。混凝土达到设计要求的可张拉的时间和强度,且具备混凝土强度试验报告单及张拉端张拉条件(如张拉场地,预应力筋张拉端混凝土清理等)后,立即张拉,不占用过多模板。2.5劳动力安排计划按土建结构施工整体部署,穿插或平行进行预应力施工。技术人员根据现场施工进度情况对现场操作人员预先进行调配,高峰时期最多可派7人,平时不少于2人。2.6施工机械设备情况根据工程进度与工作量的大小合理投入设备,本工程拟投入设备配备详见下表:编号名称规格数量备注1千斤顶、油泵、压力表23t/380v/750w1套须配套标定52灌浆泵1台3搅拌器1台4电线盘220v2套5电线盘380v2套6砂轮锯18cm/220v/750w1个配套锯片7大砂轮锯35cm/380v/1600w1个配套锯片8黑胶带1箱9工具箱1个常用工具三、工程所用材料3.1预应力筋预应力筋采用j15高强1860级国家标准低松弛钢绞线,其标准强度fyk=1860N/mm2。3.2预应力锚夹具预应力锚具采用Ⅰ类锚具,无粘结张拉端为单孔夹片式锚具,由单孔锚具、锚板、穴模、螺旋筋组成;锚固端为挤压锚,由挤压锚具、承压板、螺旋筋组成。6四、无粘结预应力施工工艺4.1无粘结预应力大梁施工工艺流程本工程无粘结预应力梁的高度大,为确保施工质量和进度,梁的侧模必须在预应力筋穿入固定后安装。施工工艺流程如下:预应力筋下料搭梁板钢管支架支梁底模、起拱和校正底标高铺放非预应力钢筋骨架划预应力筋曲线坐标位置、焊接定位筋穿入预应力钢绞线预应力钢绞线定位固定安装、固定端部张锚垫板支端模铺放其他非预应力筋预应力筋隐检,浇筑混凝土及混凝土养护拆梁侧模张拉无粘结预应力筋端头封堵拆除梁底模和支架4.2铺放前的准备工作4.2.1准备端模7端模须采用木模,若施工工艺有特殊要求也可采用其它模板。对于无粘结根据预应力筋的平、剖面位置在端模上打孔,孔径25~30mm。4.2.2准备架立筋应根据设计图纸所示,每隔1.5-4.0米设置架立筋,架立筋采用直径为12-14的螺纹钢筋,并与箍筋焊牢或绑扎牢固,以备在铺设预埋管时用。4.2.3预应力筋下料及锚固端挤压锚的组装。4.3穿预应力筋4.3.1钢绞线要定长下料。钢铰线应用砂轮锯切割,不得用电气焊切割。下料长度L=梁内曲线长度L1+张拉端工作长度L24.3.2如是多束,则采用分束多次穿入的方法。4.3.3穿预应力筋由锚固端向张拉端穿,避免扭曲。钢绞线穿入后,不得使用电气焊,以避免造成预应力筋的强度降低。4.4浇筑混凝土4.4.1检查铺设情况浇筑混凝土之前,应再次检查管道位置是否正确,数量是否正确,有无破损,如发现问题应及时改正。只有在作隐蔽工程检查合格后,才能浇筑混凝土。4.4.2浇筑混凝土时要振捣密实,尤其在端部,严禁出现蜂窝麻面等情况。4.5预应力筋的张拉4.5.1张拉的条件混凝土达到设计要求张拉强度(90%)后方可进行预应力筋的张拉。张拉前总包单位应提供同条件养护的混凝土试块强度试验报告单,如空心板中有后浇带,则应在后浇带封带并达到设计要求的张拉强度后才能张拉。4.5.2张拉设备及机具无粘结预应力筋采用YCN25前卡液压式千斤顶。根据工程量及进度情况安排适当数量的张拉设备。预应力筋张拉设备及仪表,由专人使用和管理,并定期维护和校验。4.5.3张拉前准备1、张拉端要准备操作平台,可以利用原有的脚手架,应保证宽不小于1米,原则上要求张拉工人有足够摆放机具及张拉操作空间。2、清理张拉端,记录预应力筋初始外露值。3、与承压板面不垂直的预应力筋,端部必须进行垫片处理,最终做到承压板面与张拉作用线垂直。84、根据设计要求确定单束预应力筋控制张拉力值,计算出其计算伸长值,张拉用千斤顶和油泵根据设计要求事先标定好。4.5.4张拉过程1、张拉流程:量测预应力筋初始长度→安装锚具→装千斤顶→张拉应力σcon→锁定锚具→退出千斤顶→校核预应力筋伸长值→量测预应力筋终结长度。根据规程的规定,施工时一次性超张拉设计张拉应力的3%。2、张拉中,随时检查张拉结果,理论伸长值与实测伸长值的误差不得超过施工验收规范允许范围(-6%,+6%)。否则应停止张拉,待查明原因,并采取措施后方可张拉。3、在张拉之前,板底支撑不能拆除;但是侧模可以拆除。张拉后,若施工单位经验算施工荷载小于板的设计使用荷载,则板的支撑才可以拆除。4.6张拉后张拉端处理1、张拉后,将锚具外露的预应力筋预留不少于30mm长度后多余部分用机械方法切断,在7天内做好锚具的防锈蚀工作。2、对端头的处理后,检查验收合格后,总包10天
本文标题:预应力梁施工方案(无黏结)
链接地址:https://www.777doc.com/doc-1985093 .html