I郑登快速通道改建工程第五标段(K40+869—K46+850)Y018分离式立交桥吊架梁施工方案编制:审核:批准:中建交通建设集团有限公司郑登快速通道改建工程第五标段项目经理部II目录第一章工程概况.....................................................................1第二章编制依据.....................................................................32.1编制依据...............................................................32.2施工技术规范、标准....................................................32.3编制原则.............................................................3第三章施工总体部置...........................................................43.1施工组织机构.........................................................43.2机械设备计划.........................................................43.3人员配备情况.........................................................4第四章施工准备.....................................................................74.1设备准备...........................................................................................................................74.2道路准备...........................................................................................................................74.3人员准备...........................................................................................................................84.4支座安装...........................................................................................................................84.4.1准备工作................................................................................................................84.4.2支座安装................................................................................................................9第五章施工方案....................................................................105.1梁场起梁........................................................................................................................105.2梁板运输........................................................................................................................105.3现场吊装.........................................................................................................................115.4吊装注意事项及质量检验标准....................................................................................12III第六章质量保证措施............................................................146.1质量保证体系................................................................................................................146.2组织保证措施................................................................................................................146.3技术保证措施................................................................................................................15第七章安全保证措施............................................................167.1安全管理制度................................................................................................................167.2施工人员安全措施........................................................................................................167.3移梁安全措施................................................................................................................177.4梁体吊装安全措施.........................................................................................................177.5吊车操作安全措施........................................................................................................181第一章工程概况本标段路基段落位于河南省新密市和登封市境内,施工桩号K40+869~K46+850(黑沟桥桥头)。施工里程为5.981公里。地势起伏较大,坡谷相间,地形切割较为强烈,沟谷较深,局部低山丘陵间亦有剥蚀平地。本标段有大桥两座、分离式立交三座、涵洞5道、通道1座。线路于K44+053.272与Y018相交,交角70度,主线下穿Y018(三级路),在该处设置分离式立交1处。桥梁采用2x30m装配式预应力砼组合箱梁,先简支后连续结构体系,下部结构采用桩柱式桥墩台,钻孔灌注桩基础,桥梁全长67m,桥宽10m,预制梁6片。本分离式立交涉及范围内平面位于直线段上,路线纵断面位于3.0%竖曲线上。表1-1安装吊装重量梁长部位吊装重量(吨)备注30米箱梁左边梁99.4包括钢筋、混凝土、钢绞线、孔道压浆右边梁99.4中梁92第二章编制依据2.1编制依据(1)郑登快速通道改建工程施工招标文件、设计图纸;(2)国家、交通部和沈阳市颁布的现行规范、规程与验评标准;(3)现场勘察资料;(4)公司以往从事过类似工程的施工经验;2.2施工技术规范、标准针对该工程内容,我们采用了现行的国家、交通部和沈阳市地方施工技术标准和规范,主要采用了以下的施工技术标准和规范:表2-1主要参考规范标准序号规范、标准、文件名称标准号1《公路桥涵施工技术规范》JTG/TF50-20112《公路工程质量检验评定标准》JTGF80/1-20043《公路工程安全施工技术规程》JTJ076-954《施工现场临时用电安全技术规范》JGJ46-20055《建筑机械使用安全技术规程》JGJ33-20012序号规范、标准、文件名称标准号8《施工现场机械设备检查技术规程》JGJ160-20089《起重机械安全规程》GB6067-19852.3编制原则充分考虑施工组织设计的科学性、合理性,与业主招标文件的符合性,体现我公司的施工能力和管理水平。(1)确保质量:优化施工方案,采用机械化、专业化施工,严格质量控制,使架梁施工对铁路影响降低到最小。(2)确保安全:实行严密的管理和施工措施,针对工程中可能出现安全隐患的部位和施工过程,实行重点监控,确保万无一失。(3)确保工期:鉴于本项工程的特殊性,我们一定从各种资源配置着手,按照总体工期要求,优化施工网络,实现工期目标。(4)文明施工、注重环保:在施工过程中,采取环境保护措施,做到文明施工、保护环境。2.4架设方案及运梁线路选择综合考虑到Y018(K44+052.272)为跨主线分离式立交,该桥施工进度严重制约着我标段寨东沟大桥架梁施工及主线路基施工进度,设计图中有对其进行改路改造设计,在相交处与原Y018进行顺接,设置了连接线,Y018分离式立交跨主线处为深挖石质路堑,目前正在采用机械破碎施工,且未完工,而我标段的预制梁场设置在本标段起点与S232交汇(K41+900)处,目前无法采用运梁平车将预制梁从新建主线路上运至施工地点,因此采用挂车将预制梁从S232→S316→Y018将预制梁运至施工现场。综合考虑到架梁施工成本、施工工期、场地制约、施工安全、工程量的大小(全桥仅6片预制箱梁),拟采用两台200T吊车进行该桥30m预制箱梁架设施工。第三章施工总体部署3.1施工组织机构33.2机械设备计划表3-1预制梁架设机械设备一览表序号机械设备名称机械型号数量1汽车吊200t2台2运梁拖挂车150t2辆3挖掘机LC2201台4装载机LG8501台5振动式压路机YZ14B1台6电焊机BX1-400A2台7发电机30KW2台3.3、人员配备情况项目总工:翟明丰生产经理:李平郑登快速通道改建工程第5标段项目经理部项目执行经理:杨德超桥梁工区:饶欢商务物资部:李慧芳物资设备部:董茂林安全部:金旭综合办公室:候小静质量试验室:吕新兵商务经理:李慧芳施工队4表3-2主要管理人员配备表序号姓名职务备注1杨德超项目执行经理全面负责2翟明丰总工程师技术负责人3李平生产经理现场总负责人4饶欢桥梁工区经理桥梁工区负责人5郑雷路基一工区经理一工区负责人6都兴龙路基二工区经理二工区负责人7范建成梁场分管梁场负责人8金旭安全总监施工安全管理9李慧芳商务经理合同及成本管理10董茂林物资部长物
本文标题:Y018吊车架梁专项施工方案
链接地址:https://www.777doc.com/doc-6853723 .html