您好,欢迎访问三七文档
当前位置:首页 > 建筑/环境 > 施工组织 > 某车间静压桩施工组织设计
江苏大自然食品有限公司17#主车间静压桩施工组织设计编制:校对:审核:江苏地基工程有限公司二00九年八月十日目录一、总体概述·················································································二、施工现场平面布置图··································································三、施工进度计划表和进度保证措施···················································四、各分部分项施工方案及质量保证措施···········································(一)施工方案·············································································1、施工准备工作·································································2、施工工艺及施工步骤方法·····················································3、施工注意事项···································································(二)质量保证措施···································································1、质量管理目标···································································2、技术保证措施···································································3、材料保证措施·······························································五、安全文明施工、环境保护和消防措施·············································1、安全生产目标·······························································2、安全生产保证体系··························································3、安全施工措施································································4、方明施工、环境保护措施···················································5、消防措施······································································六、项目管理班子人员配备情况·························································七、劳动力、施工机械设备及材料的投入计划和进退场计划···················八、关键施工技术、工艺及工程项目实施的重点、难点和解决方案·······九、雨季、夜晚施工措施····································································十、保证工期措施··········································································十一、新技术、新产品、新工艺、新材料的应用······························十二、地下管线及其他设施的加固、保护等特殊措施·····························一、总体概述㈠、工程概况:拟建江苏大自然食品有限公司17#主车间位于涟水开发区。该工程由江苏城建校建筑规划设计院设计。设计采用预应力管桩处理地基,工程桩选用江苏省标准图集《先张法预应力混凝土管桩》苏G03-2002,桩型为PHC—400(90)A—C80-23M。桩端持力层为10层粘土层,桩尖进入持力层不少于1米。㈡、总体施工部署2.1、总体施工进度划分⑴施工准备施工机械进场并调试、施工用电的设置、临时设施的搭建、预制管桩进场、定位放线⑵工程施工桩位复核、压桩施工、压桩孔洞回填⑶桩基检测和验收动载或静载进行桩基测试、桩位偏差的测量、桩基验收、资料整理归档2.2、机械设备安排(见下表)计划投入的机械设备表设备名称规格型号现状数量何时到工地静压桩机YZY-600良好1开工前1天电焊机ER50-6良好1开工前1天电子经纬仪ET-02良好1开工前1天水准仪DS3良好1开工前1天2.3、人员安排⑴现场机构设置(见下页)管理网络图⑵计划投入的人员表序号工作名称单位数量进场日期备注1项目经理名1开工前3天2施工员名1开工前3天3技术员名1开工前3天4材料员名1开工前3天5预算员名1开工前3天6安全员名1开工前3天7质检员名1开工前3天8电焊工名4开工前3天9电工名1开工前3天10操作工名6开工前3天项目经理施工负责人(施工员)技术负责人安全员忠心耿耿质检员沉桩班组管桩厂制作车间11普工名6开工前3天12后勤名1开工前3天二、施工现场平面布置图(见总平面图)三、施工进度计划及保证措施、材料进场计划及保证措施㈠、施工进度计划表(见附表)㈡、施工进度保证措施:1、压桩采用16小时施工,从早到晚息人不息机。2、合理安排施工进度。3、加强机械维护保养,现场备齐备足易损机械零配件,保证机械设备高效运转。4、加强施工管理,做好各工序的衔接,缩短停歇时间。所有可实行平行作业的工序,实行平行作业,决不允许影响连续工序的时间。5、做好雨天施工防护措施。6、实施经济激励机制,对速度快、质量好的班组进行物质及经济奖励,提高员工的施工积极性。㈢、材料进场保证措施在机械设备进场后一天进行管桩进场以保证能满足施工机械进场按时开工。(1)、桩型分别堆放,按施工进度、施工行驶路线进行,桩进场按制桩日期的先后进行,确保不因桩型不对而造成误工。(2)、运桩管桩由我施工单位组织运输。运输道路由建设单位的提供。(3)、管桩装卸时应轻起轻放,吊运过程应保持平稳。①、吊桩的设备机具需安全可靠、牵具、夹具须经计算有足够的强度。吊桩用钢丝绳索具长度应一致,吊桩时夹角≤90°。②、预制桩转运过程中,应按设计吊点位置搁置好垫木,车辆行驶保持平稳,避免激剧振动和撞击。装卸过程应轻吊轻放,防止损伤桩体。四、各分部分项工程施工方案及质量保证措施㈠、施工方案1、施工准备工作1.1考虑到施工现场情况,首先应进行场地处理,确保桩机所需地耐力能满足施工要求,根据甲方要求工程确保一台YZY-320T静压桩机进行施工。根据现场实际情况,场地需平整处理,且地面下大的混凝土块需要排除。1.2为确保桩机顺利作业,桩机进场正常施工及时安排施工区域四周排水沟及集水井,以保证及时将雨水及其它影响施工的集水排出场地。1.3临时设施,我方安排两个占地约50M2集装箱作为办公室、宿舍区、工具室,在施工入口处设立施工概况牌。1.4场地保证三通一平,电通,由业主提供380/220V电力源,本机启动电力需150KW。1.5预制管桩由我方供应,管桩计划提前5天报给管桩厂1.6汇同甲方、设计、监理及有关单位进行设计图纸交底会审,做好会议交底记录。1.7根据设计图纸、交底记录以及有关规范、图集,组织施工人员学习、熟悉图纸内容,并逐级做好技术交底工作,使操作人员人人对该工程的施工心中有数。1.8配合规划部门进行角桩定位放线,及各桩位放线,做好定位放线验收记录。同时保护好甲方提供的水准点及坐标控制点。1.9本工程根据现场总体场地情况和施工特点,施工顺序如下:根据现场总体场地情况和施工特点:桩基施工过程中,我施工单位从南向北施工.2、施工工艺及施工步骤方法2.1静力压桩的施工工艺测量定位压桩机就位吊桩喂桩桩身对中调直送桩接桩接桩终止压桩2.2桩位放样:2.2.1桩位放样:根据规划桩轴线,进行各桩位的平面放样,样桩用小竹签标识,顶端部涂以红漆,使得目标明显,利于检查与核对,同时主轴线引测至桩基施工场区以外,标注上各轴线名称。2.2.2桩位验收:2.2.2.1施工测量员放样完毕后,报技术部进行验收,自检合格后,填写定位放线验收记录表,报请甲方及监理进行复验。2.2.2.2桩位放样允许误差≤2cm,超出该要求的桩位进行校正。2.3压桩机就位经选定的压桩机进场安装调试好以后,行至桩位处,使桩机夹持钳口中心(可挂中心线陀)与地面上的样桩基本对准,调平压桩机,再次校核无误,将长船落地受力。2.4吊桩喂桩用压桩机上的工作吊机自行吊桩喂桩,当桩运至桩机附近后,采用一点起吊法使桩身竖直进入夹桩的钳口中。2.5桩身对中调直当桩被吊入夹桩钳口后,由指挥员指挥吊机司机将桩徐徐下降至桩尖离地面10CM左右为止,然后夹紧桩身,微调压桩机使桩尖对准桩位、并将桩压入土中0.5~1.0米,暂停下压,从两个正交侧面校正桩身垂直度,待其偏差小于0.5%时方可正式压桩。2.6压桩压桩是通过主机的压桩油缸伸程之力将桩压入土中,然后松夹,上升,再夹,再压,如此反复进行,将一节桩压下。2.7、接桩2.7.1当下节桩被压入地面仅剩余0.60~0.80米时停压,吊上节桩。施工中,分为上节桩和下节桩。2.7.2管桩对接前,应用钢丝刷清理上、下桩节的端板,坡口处应刷至露出金属光泽。2.7.3桩采用对称焊接法。把上节桩提升就位于下节桩桩顶上,校正桩身垂直度,使得上、下节桩中心线重合,桩顶吻合(有空隙处用铁片垫实)。在桩坡口圆周上对称点焊4-6点,待上下节桩固定后再对称焊接。焊缝应饱满、无气孔、无焊瘤、无裂缝,电焊厚度宜高出坡口1mm。2.7.4接桩完毕后,焊好的焊接接头应自然冷却后,才可继续沉桩,自然冷却时不应小于8分钟,严禁用水冷却和焊好即沉。2.7.5做好自检记录和施工记录,通知业主、监理进行隐蔽工程验收。符合规定后,方可压桩。每一根桩应一次连续压到底,接桩,送桩中间不得无故停歇,尽量缩短的时间。2.8、送桩对桩顶已达设计标高,而仍未达规定的压桩力时,应及时将施工记录报送监理工程师,根据监理工程师指令方可继续施工;当压桩力达到规定,而桩顶未达设计标高时,也应及时将记录报送监理工程师,根据监理工程师指令方可继续施工。采取桩长压桩力双控的办法压桩。2.9压桩结束当达到设计要求或压力表读数达到设计值时,便可以停止压桩(送桩)截掉余桩(具体情况依据设计交底会议成果),严禁用大锤硬砸截桩,应先将不需要截除的桩身端部用钢箍抱紧,然后用钜桩器将多余的桩截掉。3、施工注意事项3.1施工前应对现场的土层、土质情况了解清楚,同时应做好设备的检查工作,防止压桩过程中出现事故而使压桩中断,引起间隙后压桩阻力过大,发生压不下去的事故。电梯承台下桩位较密,桩基施工过程中,我施工单位看实际情况,如压力过高,在电梯承台四周挖沟,措施减少对周围建筑物的影响。3.2压桩机应根据土质情况配足额定重量。3.3施压过程中应保证桩的轴心受压,始终保持桩帽、送桩的轴线重合,如有偏斜,要及时调整。3.4压同一根桩应连续进行,应尽量缩短间歇时间。3.5压桩过程中,当桩尖碰到夹砂层时,桩尖阻力增大,导致桩压不下去。这时应以最大压桩力压桩,忽停忽开,使桩有可能缓缓下沉穿过夹砂层。㈡、质量保证措施我公司本着“百年大计,质量第一”的方针,以“质量就是生命”为指导思想,坚持质量就是信誉,质量就是效益的观念,对每一项工程实施全面质量管理。为确保本工程质量达到一次验
本文标题:某车间静压桩施工组织设计
链接地址:https://www.777doc.com/doc-7157875 .html