地形平坦开阔,地层由第四系全新冲积层,第四系上更新统冲层组成,局部表覆第四系全新统人工堆积层。第四系全新统冲积层厚度约25~50m,岩性主要为黏土、粉质黏土、粉土、粉砂、细砂;第四系上更新统冲积层厚度大于50m,岩性主要为黏性土、粉土、粉细砂等。管桩深度范围内地层主要为:粉土、黏土、粉质黏土,局部表层为杂填土。couplingCentreshallbechecked,thesecondpouredconcretestrengthofmorethan70%.Intheprocessofreamingorboring,apartfromthespecialprovisionsinfactory,doesnotallowanyworkthatmayaffectthecouplingCentre,suchasirrigation,tocylinderconnectionstofloodthecondenserpipesandsoon.Wellboring,hingeboltholeflangewithcouplingofvertical,notoblique.Mountingboltsshouldbeaddedlubricants,typinggentlywithasmallhammer,nottoolooseortootight,packedtheboltswiththecorrespondingsealscrewholeshouldbemarked.6.4.5.4.2couplingreamedandpairingsisclosetothediameterofboltbearinggoodhingeholes,dressedwithagoodtwocouplingboltsbeforeyoucanmovetherotor,boring-reamingholeinturn.Couplingboltsmustbetightcouplingissymmetricaldiameter,inboring,reaming,twoboltsout.Wellboring,hingeboltholeflangewithcouplingofvertical,notoblique.Duetothecouplingboltsinaccordancewithhingeholescorrespondingtothediameterofthescrewholesonebyoneafterprocessing,processingbackboltinstallationlocationcannotbechanged,soaccordingtoboltaftertheactualweightdifferenceofnutandlockwashertomatch.Generalrequirementsforcouplingtwosymmetricaldiameterbolt,nutandlockwasher'stotalweightdifferenceshouldnotbegreaterthan10gandknocksstampedmark.(SeeFigure18)Thecouplingboltsapplylubricant,andthengentlywithcopperhome,nottoolooseortootight.BoltAssemblyisfinished,symmetricaltighteningallboltsto30%,50%,70%,100%force,andcheckthecouplingflutterandbeforeconnectingthecirclegraduallychangesitsvalueshouldbelessthan0.02mm.Tighteningtorqueofthecouplingboltsshallcomplywiththetechnicalrequirementsmanufacturersdrawings,withadynamometricwrenchorlogtensiontools.Threewheelrotorswingtestcouplingconnectionsshouldbechecked:takingleave,G207线道县祥霖铺至江华界牌井公路改建工程项目“首件工程认可制”实施细则为了加强工程施工质量(内在质量、外观质量、档案质量)的管理,努力消除质量事故隐患,杜绝质量通病,进一步提高现场管理水平,依据《湖南省干线公路建设实施首件工程认可制指导意见》(湘路工建[2010])241号,下文简称“指导意见”)及省、市公路局的相关规定,特制定本实施细则。本细则主要按“指导意见”,对其部分章节进行细化、补充、完善而编制成。一、关于“首件工程的目的和作用”的深层认识1、由于不同的工程项目是在不同的环境下进行的,材料、人员、设备、工艺、地理条件、安全环保要求等均发生了变化,这些变化将不同程度地影响到工程质量,通过首件制工程,可以评价对工程质量影响程度。2、通过首件工程的实施,便于承包人施工工艺组合,总结经验,加强管理,为规范化施工创造条件。3、通过首件工程的实施,可预见施工中遇到的各种问题,特别是解决有可能影响工程质量的各种因素,对出现的问题及时处理,减少了承包人的损失,避免施工后期造成返工。4、通过首件工程的实施,熟悉设计规范和技术要求,根据项目特点,确定表面质量等级及验收标准,落实业主对具体分项的特殊要求。二、首件工程认可组织机构首件工程检评工作组由以下单位的全部或部分组成:1、项目业主质量监督组(总监办);地形平坦开阔,地层由第四系全新冲积层,第四系上更新统冲层组成,局部表覆第四系全新统人工堆积层。第四系全新统冲积层厚度约25~50m,岩性主要为黏土、粉质黏土、粉土、粉砂、细砂;第四系上更新统冲积层厚度大于50m,岩性主要为黏性土、粉土、粉细砂等。管桩深度范围内地层主要为:粉土、黏土、粉质黏土,局部表层为杂填土。couplingCentreshallbechecked,thesecondpouredconcretestrengthofmorethan70%.Intheprocessofreamingorboring,apartfromthespecialprovisionsinfactory,doesnotallowanyworkthatmayaffectthecouplingCentre,suchasirrigation,tocylinderconnectionstofloodthecondenserpipesandsoon.Wellboring,hingeboltholeflangewithcouplingofvertical,notoblique.Mountingboltsshouldbeaddedlubricants,typinggentlywithasmallhammer,nottoolooseortootight,packedtheboltswiththecorrespondingsealscrewholeshouldbemarked.6.4.5.4.2couplingreamedandpairingsisclosetothediameterofboltbearinggoodhingeholes,dressedwithagoodtwocouplingboltsbeforeyoucanmovetherotor,boring-reamingholeinturn.Couplingboltsmustbetightcouplingissymmetricaldiameter,inboring,reaming,twoboltsout.Wellboring,hingeboltholeflangewithcouplingofvertical,notoblique.Duetothecouplingboltsinaccordancewithhingeholescorrespondingtothediameterofthescrewholesonebyoneafterprocessing,processingbackboltinstallationlocationcannotbechanged,soaccordingtoboltaftertheactualweightdifferenceofnutandlockwashertomatch.Generalrequirementsforcouplingtwosymmetricaldiameterbolt,nutandlockwasher'stotalweightdifferenceshouldnotbegreaterthan10gandknocksstampedmark.(SeeFigure18)Thecouplingboltsapplylubricant,andthengentlywithcopperhome,nottoolooseortootight.BoltAssemblyisfinished,symmetricaltighteningallboltsto30%,50%,70%,100%force,andcheckthecouplingflutterandbeforeconnectingthecirclegraduallychangesitsvalueshouldbelessthan0.02mm.Tighteningtorqueofthecouplingboltsshallcomplywiththetechnicalrequirementsmanufacturersdrawings,withadynamometricwrenchorlogtensiontools.Threewheelrotorswingtestcouplingconnectionsshouldbechecked:takingleave,2、监理单位:驻地监理处;3、施工单位项目部总监办及驻地监理处负责对施工方案、工艺方案、安全措施、工程材料进行审核并监督实施,统一报检程序和检表格式,对首件工程进行初检。经施工单位初检后,驻监处初检后,总监办牵头由相关单位组成质量检评组,对首件工程进行全面检查验收。三、“首件工程认可制”的评价标准1、业主用于质量管理与控制的相关文件规定,及业主对所属工程项目招标文件;2、《公路工程质量检验评定标准》(JTGF80/1-2004)和有关规范;3、湖南省交通运输厅制定的有关制度和办法。四、首件工程申报、实施、检查验收流程地形平坦开阔,地层由第四系全新冲积层,第四系上更新统冲层组成,局部表覆第四系全新统人工堆积层。第四系全新统冲积层厚度约25~50m,岩性主要为黏土、粉质黏土、粉土、粉砂、细砂;第四系上更新统冲积层厚度大于50m,岩性主要为黏性土、粉土、粉细砂等。管桩深度范围内地层主要为:粉土、黏土、粉质黏土,局部表层为杂填土。couplingCentreshallbechecked,thesecondpouredconcretestrengthofmorethan70%.Intheprocessofreamingorboring,apartfromthespecialprovisionsinfactory,doesnotallowanyworkthatmayaffectthecouplingCentre,suchasirrigation,tocylinderconnectionstofloodthecondenserpipesandsoon.Wellboring,hingeboltholeflangewithcouplingofvertical,notoblique.Mountingboltsshouldbeaddedlubricants,typinggentlywithasmallhammer,nottoolooseortootight,packe
本文标题:首件工程实施细则
链接地址:https://www.777doc.com/doc-5195997 .html