您好,欢迎访问三七文档
当前位置:首页 > 建筑/环境 > 电气安装工程 > PTF-101电气整套启动调试方案
第1页共24页电气整套启动调试方案平顶山第二发电厂一期2×1000MW机组工程调试作业指导书PTF-DQ101平顶山第二发电厂一期2×1000MW机组工程调试作业指导书河南电力建设调试院第2页共24页工程名称平顶山第二发电厂一期2×1000MW机组机组编号#1机组文件名称电气整套启动调试方案文件类型整套启动调试项目部批准年月日审核年月日编写年月日平顶山第二发电厂一期2×1000MW机组工程调试作业指导书河南电力建设调试院第3页共24页目次1目的·············································································································42编制依据·····································································································43设备系统简介······························································································44调试内容及质量指标··················································································75组织分工·····································································································86仪器设备的配置··························································································97调试应具备的条件······················································································98调试步骤···································································································109安全健康与环境要求················································································1910附录·········································································································20平顶山第二发电厂一期2×1000MW机组工程调试作业指导书河南电力建设调试院第4页共24页1目的规范机组电气整套启动调试工作程序,确定各系统设备整套启动的试验项目和操作步序,明确整套启动各阶段电气专业调试工作的任务和参与整套启动调试工作各方的职责,确保机组整套启动工作安全、可靠、顺利地完成。2编制依据2.1《火力发电建设工程启动试运及验收规程》(DL/T5437-2009)。2.2《火电工程启动调试工作规定》(建质[1996]40号)。2.3《火电工程调整试运质量检验及评定标准》(建质[1996]111号)。2.4《电气装置安装工程电气设备交接试验标准》(GB50150-2006)。2.5《电力工程投产达标管理办法》(中电建协工[2006]6号)。2.6《电力建设安全健康与环境管理工作规定》(国家电网工[2003]168号)。2.7《国家电网公司电力安全工作规程(变电部分)》(国家电网安监[2009]664号)。2.8《国家电网公司发电厂重大反事故措施(试行)》(国家电网生[2007]883号)。2.9《国家电网公司十八项电网重大反事故措施》(国家电网生技[2005]400号)。2.10《调试管理细则》(中电投电力工程有限公司鲁阳项目)。2.11《试运组织机构管理程序》(中电投电力工程有限公司70411010000-2008)。2.12《电力建设工程预算定额》调试工程(中电联技经[2007]15号)。2.13机组调试大纲。2.14设计、设备相关资料。3设备系统简介3.1设备系统概述本期工程为2×1000MW超超临界燃煤汽轮发电机组,两台机组采用发电机-变压器组接入厂内500kV母线,发电机出口不装设断路器。500kV本期出线2回接入香山500kV变电站。厂内500kV开关站采用一个半断路器接线,本期设两个完整串,电源回路与出线回路配对成串,接于500kVⅠ、Ⅱ母线。两台机组设一台容量为78/45-45MVA高压启动/备用变压器,高压侧由500kVⅠ段母线引接,采用有载调压方式,其低压10kV侧通过共箱母线与#1、#2机组的10kV工作ⅠA、ⅠB、ⅡA、ⅡB段连接。每台机组设一台高压厂用工作变压器,采用78/45-45MVA的分裂变压器,高压厂用变压器为无励磁调压方式,其电源由发电机出平顶山第二发电厂一期2×1000MW机组工程调试作业指导书河南电力建设调试院第5页共24页口引接。每台机组设两段10kV工作母线,从高厂变低压侧引接,向本单元厂用负荷供电。设置有10kV输煤A、B段,电源分别由10kV工作ⅠA、ⅡA段引接。主变、启动/备用变压器中性点采用直接接地方式,发电机经接地变高阻接地(1.4Ω)。10kV高压厂用电系统采用在高厂变及启动/备变低压侧中性点经中电阻接地的方式,相应接地电阻为60Ω、100A。低压厂用电电压为380/220V,采用中性点直接接地方式。低压厂用电系统采用动力中心和电动机控制中心即PC-MCC的供电方式。发电机变压器组接入厂内500kV配电装置,设升压站继电器小间,布置升压站计算机监控系统(NCS)采集单元、线路保护设备、升压站直流系统等设备。发变组和厂用电源的控制纳入电厂DCS系统。在DCS中控制和监测的电气设备和元件有:发电机变压器组系统、厂用电系统、高压启动/备用变系统、保安电源、直流和UPS系统等。500kV系统保护配置:线路保护采用南瑞继保公司的PRC31AM-54型和许继公司的GXH803A-201G型双重光纤保护装置;母线保护选择深圳南瑞继保公司的BP-2B型和许继公司GMH800A-109S型保护装置;断路器保护采用南京南瑞继保公司的PRC21A/22A型保护装置。500kV系统配置了由武汉中元生产的ZH-3型故障录波装置。发变组、启动/备用变配备南瑞继保公司的RCS-985B/T型保护,按双套主、后备保护和单套非电量保护配置。发变组、启动/备用变系统分别配置了山东山大公司的WDGL-V型故障录波装置。发电机自动励磁调节装置采用GE公司生产的EX2100型设备,励磁系统主要由三相全控桥式整流装置、灭磁及转子过压保护装置、起励装置、微机励磁调节器和励磁变压器组成。每台机组装设一套(两台主机冗余并列)交流不停电电源装置(UPS),向集控室需要不间断供电的机组DCS、热工保护、火灾报警设备、电气厂用电监控系统、远动设备等提供交流电源,以确保机组可靠正常运行。每台机组设置三组阀控式铅酸蓄电池,其中两组110V蓄电池组向控制、保护、测量等负荷供电,一组220V蓄电池组向事故照明、动力负荷和交流不停电电源等负荷供电。蓄电池组正常均以浮充电方式运行。每台机组设置一台1800kW柴油发电机组作为机组的事故保安电源。事故保安电源分别设置汽机事故保安PC及锅炉事故保安PC。平顶山第二发电厂一期2×1000MW机组工程调试作业指导书河南电力建设调试院第6页共24页3.2电气主要一、二次设备技术规范序号名称型号制造厂技术参数1发电机QFSN-1000-2哈尔滨电机厂1111MVA,27kV,23950A,cosφ=0.9UfN=563V,IfN=5360A,2主变DFP10-390000/500天威保变550/3-2×2.5%/27kV,3×390MVA,YNd11,Ud=20%3高厂变SFF10-CY-78000/27特变沈变78/45-45MVA,27±2×2.5%/10.5-10.5,Ud=18%,DYn1-Yn14启备变SFFZ-CY-78000/500特变沈变78/45-45MVA,Ud=19%,YNyn0,yn0,d,525±8×1.25%/10.5-10.5kV5500kV断路器GL317X苏州阿海珐550kV,4000A,63kA6500kV隔刀GW16B/17B-550河南平高550kV,4000A7500kV地刀1GW16B/17A河南平高550kV,4000A8500kV地刀2JW8A河南平高550kV,630A9500kVPTWVB-500-5H日新电机1.0/31.0/31.0/350010500kVCTSKF-550上海雷兹2×2000/111励磁变ZLDCB9广东顺特(单相)3×3700kVA,27/1.2kV1210kV干式变SCB10-1600/10北海银河10.5±2×2.5%/0.4kV;Dyn1113发变组保护RCS-985B南京南瑞微机型发变组保护装置14励磁装置EX2100GE公司自并励静态励磁系统15同期装置SID-2CM深圳智能可选择控制两个同期点16发变组故录WDGL-V/F山东山大100V/57.7V,1A,50Hz,DC110V17启备变保护RCS-985T南京南瑞启备变本体保护18启备变故录WDGL-V/B山东山大100V/57.7V,1A,50Hz,DC110V19厂用电快切MFC2000-3A江苏金智高压厂用电微机快速切换装置20线路保护ⅠPRC31AM-54南京南瑞线路微机光纤分相差动保护及远跳21线路保护ⅡGXH803A-201G许继继保线路微机光纤分相差动保护及远跳22母线保护ⅠBP-2B深圳南瑞母线差动保护23母线保护ⅡGMH800A-109S许继继保母线差动保护24断路器保护PRC21A/22A南京南瑞辅助保护25500kV故录ZH-3武汉中元100V/57.7V,1A,50Hz,DC110V26NCS测控装置YOYQA南京南自500kV控制、测量、监视系统平顶山第二发电厂一期2×1000MW机组工程调试作业指导书河南电力建设调试院第7页共24页27功角测量SMU-2G国电南瑞同步相量测量装置28微机远动RTUD20ME上海惠安机组至调度遥测、遥调、遥控2910kV综合保护测控装置TOP9720珠海拓普用于10kV电动机、干式变、馈线30380V综合保护测控装置LPC1-5XX江苏金智用于380V电动机、馈线31110V直流ZZG13B-50110许继电源主厂房110V直流电源屏32220V直流GFMD-1800Ah许继电源主厂房220V直流电源屏33UPS电源SDP31080-220青岛埃迪森主机柜、旁路稳压柜、馈线柜34柴油发电机DEEPSEA康尔信1800kW/400V4调试内容及质量指标调试内容及质量指标(依据验评标准)见下表:试运阶段调试内容质量目标升速阶段1.在超速前后的额定转速下的交流阻抗和功率损耗。试5-4-12.发变组短路试验:二次电流回路检查;励磁系统初查;发变组保护检查;短路特性曲线录取;发电机及变压器等一次系统检查。试5-4-23.发变组空载试验:二次电压回路检查;发变组保护及自动装置检查;空载特性曲线录取;测量额定电压下轴电压;发电机及变压器等一次系统检查;励磁系统特殊试验;测量灭磁后发电机定子残压及相序。试5-4-34.励磁系统动态试验:自动方式升压及电压调节范围;手控方式升压及电压调节范围;手控方式与自动方式相互切换试验;5%阶跃试验;手控零起升压;自动零起升压;频率特性;录取发电机灭磁时间常数;励磁系统各种限制等特性试验;励磁系统特殊试验。试5-
本文标题:PTF-101电气整套启动调试方案
链接地址:https://www.777doc.com/doc-116634 .html